Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assetsbasedon the construction-in-process cost of each asset.Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)

A.

Standard Unit Cost

B.

Actual Unit

C.

Current Cost

D.

Estimated Cost

E.

Spread Evenly

Your company uses an accounting calendar with periods that are identical to calendar months. A contract resource has been identified to work for six months on an accounting close cycle project. The resource is planned to start with 10 days left in the first period and to end 20 days into the last period. For the remaining periods, the resource must be loaded on all working days of the month. You are required to distribute the budget, forecast, and planning amounts across periods based on the task duration.

Which predefined spread curve must be used to meet this requirement? (Choose the best answer.)

A.

Daily Spread Basis

B.

Back Loaded

C.

Bell Curve

D.

S-Curve

E.

Even

You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).

Then Bill Plan A is allocated against Project X – Task 10, and Bill Plan B is allocated against Project Y – Task 30.

Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)

A.

Both the contract lines create only a single invoice because they are using the same contract.

B.

Two invoices are created using the same contract.

C.

Bill set number drives the grouping of transactions.

D.

Invoice generation does not depend on bill plan. The invoices are created based on the contract line.

Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)

A.

Create a revenue method with a revenue method classification of Amount Based.

B.

Create a revenue method with a revenue method classification of Rate Based.

C.

Create a revenue method classification with a revenue method of Percent Spent.

D.

Create a revenue method classification with a revenue method of Percent Complete.

As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes in HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers. (Choose the best answer.)

A.

Pool Membership

B.

attributes that the project enterprise resources are assigned after creation

C.

Jobs

D.

Person Type

Which two statements are true about the cross-charge method, Borrowed and Lent?

A.

This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations within a legal entity.

B.

Costs or revenue are shared based on transfer price rules with this method.

C.

You must set up the contract business unit to use this method.

D.

This method creates a formal internal invoice.

Your customer accounts revenue based on, product class category. Because all your customer's projects are funded by private and government institutions, they decide to classify all projects based on their funding source to accurately report on revenue in General Ledger. Accordingly, you create a new class category “Funding Source” and assign it to all projects. However, you notice that the accounting is still happening based on product class category. Identify the reason for this problem. (Choose the best answer.)

A.

Funding source class category is assigned to all project types.

B.

Funding source class category is not enabled for “available as accounting source”.

C.

Product class category is not enabled for “available as accounting source”.

D.

Funding source class category is enabled for “available as accounting source”.

Your organization wants to capture the project details for work order labor and equipment resource transactions as part of a project-driven supply chain solution.

Which expenditure type class is recommended for the expenditure types that need to be defined for these type of transactions?

A.

Supplier Invoice

B.

Work In Process

C.

Usages

D.

Inventory

You search for resources to fulfill a project resource request but are unable to proceed after receiving the following error message: “The search for resources cannot be completed because the project resource search index is not available. Contact your help desk.”

Identify the cause for this error message. (Choose the best answer.)

A.

The index is not in the process.

B.

The index has been built.

C.

The index is in the process of being updated.

D.

The most recent update of the index finished successfully.

Your customer has separate organizations to maintain indirect, capital, and billing types of projects.

Identify the two setups that can be used to fulfill this requirement. (Choose two.)

A.

Project Type

B.

Business Unit

C.

Project Organization Classification

D.

Organization Tree

E.

Project Accounting Business Function