Which of the following is a step in estimating the consequences of releasing a hazardous material into the surrounding environment?

A.

Estimating the release rate

B.

Identifying the most likely failure mode

C.

Determining the deterioration susceptibility and rate

D.

Identifying active and credible damage mechanisms

The fact that some jurisdictions may have some prescriptive time-based rules on inspection intervals does not preclude the user from gaining significant benefits from the application of RBI, as long as:

A.

local regulations do not specifically prohibit the use of RBI planning.

B.

the inspection intervals do not exceed half-life or 10 years maximum.

C.

the RBI process methodology is in accordance with API RP 581.

D.

the RBI process is implemented by an API 580 certified individual.

What will affect the level of risk mitigation achieved in RBI?

A.

The established frequency of inspection for higher risk equipment

B.

The quality of the inspection data and the analysis or interpretation of that data

C.

Replacement of equipment instead of continuing to inspect it after half-life is attained

D.

Upgrading the metallurgy of equipment to higher alloys which are more corrosion resistant

Which of the following statements is correct with regard to the potential reduction of inspection cost by using RBI?

A.

Equipment integrity is the focus.

B.

RBI will eliminate many internal inspections.

C.

On-stream inspections are as effective as internal inspections.

D.

RBI will probably raise the total cost of inspection for a given unit.

An RBI assessment of new equipment or a new project may:

A.

not be useful because there is no inspection history.

B.

be needed in order to define the risk criteria to be used in service.

C.

be conducted only after 1000 hours of operation to establish operating and inspection data.

D.

yield useful information on potential future risks.

Once organizing the work process for RBI program planning has been completed, the next step is the identification of the:

A.

appropriate mitigation activities that will be considered.

B.

credible damage mechanisms and failure modes.

C.

applicable design and inspection codes and standards.

D.

data and information required to be collected for RBI analysis.

What is one goal of a risk matrix or risk plot?

A.

To understand how consequence and probability of risk varies between different levels of risk

B.

To communicate the results of a risk assessment in a common format that a variety of people can understand

C.

To show ISO-risk lines and boxes on a matrix and determine which risks are acceptable and which are not

D.

To determine what level of risk is acceptable to management based on consequence and probability of failure

The POF analysis shall address what type of damage mechanisms to which the equipment being reviewed can be susceptible?

A.

All corrosion and cracking damage mechanisms

B.

All damage mechanisms in API RP 571

C.

All potential damage mechanisms

D.

All credible damage mechanisms

Depending on factors such as the remaining life of the equipment and the type of damage mechanism, risk management through inspection:

A.

results in a decrease in inspection frequencies.

B.

is the least cost-effective.

C.

may have little or no effect.

D.

is most effective in reducing risk.

One of the steps in estimating the consequences of releasing a hazardous material includes:

A.

identifying the most likely failure mode.

B.

estimating total volume of fluid that may escape.

C.

determining the deterioration susceptibility and rate.

D.

identifying active and credible damage mechanisms.