(During the Foundations phase, Brinda Vyas organized a workshop that Hira facilitated. It was attended by Sukra Aroon, Mira, Lee Tan, and Developers from the two Delivery Teams. The goal was to define and align on what would be available for guests at the end of Project Increment 4.

Considering the workshop attendees, which of the following observations aligns with AgilePM?)

A.

Mira Bachar ' s attendance was valid, because the Product Owner ensures Delivery Teams deliver value and stay on schedule.

B.

Mira Bachar ' s attendance was valid, because the Product Owner resolves technical and design conflicts.

C.

Sukra Aroon ' s attendance was unnecessary, because the Solution Architect is only needed during development.

D.

Sukra Aroon ' s attendance was unnecessary, because technical discussions should be separate from solution planning to avoid overcomplicating.

E.

Co-creating the vision was appropriate, because AgilePM stresses early collaboration to achieve shared understanding of project goals.

F.

Co-creating the vision was necessary, because AgilePM requires full solution design in Foundations.

G.

Hira should NOT have facilitated, because Brinda Vyas should lead all project vision discussions.

(New food hygiene laws take effect in six months. Sukra Aroon and Wanida Anong are assessing if kitchen remodeling is needed, which may divert Infrastructure Team resources.)

A.

Approach-based, because past Project Increment planning failed to account for regulatory change, causing lack of contingency and resource risks.

B.

Approach-based, because Sukra Aroon should have tracked evolving legislation from the start to mitigate the risk.

C.

VUCA-based, because new legislation is an external factor requiring adaptability to respond to unplanned demands.

D.

VUCA-based, because gaps in internal compliance cause uncertainty in responding to changing regulations.

(Wanida Anong, working on some compliance issue in India, has limited availability to work with the Southeast Asia Delivery Teams.

Which 2 statements describe how this risk should be handled within the AgilePM framework?)

A.

Hira should coordinate a communication plan to ensure the Delivery Team has timely access to Wanida ' s expertise based on her availability.

B.

Hira should escalate to Sarah Lark, the Business Sponsor, to allocate more compliance resources and protect the projects integrity.

C.

Hira should use the Risk Log to record risks and delay compliance-sensitive features until Wanida Anong is available.

D.

The Delivery Team should compile key compliance questions in advance and send in batches to Wanida Anong to minimize real-time communication needs.

E.

The Delivery Team should proceed with assumptions and review with Wanida Anong at the end of the increment to minimize delays.

Most of the Customer Services staff are working with the new processes. However, there are a number of remaining staff who don’t want to be trained in the new technologies and wish to continue supporting the old business areas.

Which is the MOST appropriate intervention from the Customer Service Director?

A.

Identify workarounds for those staff who resist the new processes so that they can remain operating within the new structure.

B.

Maintain a listening stance, showing interest in understanding the reasons for the discomfort that many are feeling over the changes.

C.

Shock staff into action by telling them that some staff will lose their place in the organization if they are unable to make adjustments.

D.

Consider leaving some of the existing structure unchanged so that those who may not find the change workable can be accommodated.

Using the additional information provided for this question in the Scenario Booklet, answer the following question about the actions the Sales Director should

take to develop an effective Sales management team, according to the five dysfunctions that characterize an ineffective team identified by Patrick Lencioni.

Lines 1 to 4 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Which 2 actions demonstrate connectivity?

A.

Arrange a number of briefing sessions for Customer Services staff, over lunch times and in a comfortable setting.

B.

Make short videos available showing how customer service teams from other companies effectively provide services for these types of offerings.

C.

Create a central area on the UniCo internal shared work system for the Change Programme to collaborate and comment on the materials.

D.

Ask the senior leadership to provide examples of other companies undertaking, and successfully overcoming, similar challenges.

E.

Send the plans of the new office layout to the Selco staff showing them where each individual will be located.

The Customer Services Director has announced the new structure at a large presentation for all Customer Services staff. The scale and design of the change have surprised many of the staff.

In the weeks immediately following the Customer Services Director’s initial presentation, there have been rumors of the Help Desk staff talking unhappily in small groups, with blame directed at " the management " for a recent period of poor performance of the department.

Which approach is the MOST appropriate way for the Customer Services Director to create early involvement in the change?

A.

Target those staff in the Help Desk who are change-averse so that they are the first ones involved in the program.

B.

Delay communications a few weeks so that all staff have time to think for themselves about the benefits of the new structure.

C.

Identify those staff who would be willing to trial new Help Desk processes and work on pilots in the department.

D.

Encourage the Help Desk staff to begin setting goals for themselves under the new structure.

The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.

Which action is MOST likely to promote success in the induction of the change agent network to the Operational delivery processes workstream?

A.

Allocate bonus payments to change agents who deliver quicker than planned.

B.

Ensure that the CEO, as Sponsor, allows time to get to know the change agents.

C.

Transfer the change agents for a short period to help the other three workstreams.

D.

Negotiate that the change agents have direct authority to implement changes.

The Change Manager has read Goleman ' s articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that

leadership style can improve organizational culture and performance as measured by staff surveys.

Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the

organization.

Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each

recommendation in Column 1, select from Column 2 the ' dimension ' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be

used once, more than once or not at all.

Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:

Hydrotherapy in Mineral-Rich Spring Pools

Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote

deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush

and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.

In addition to the Developers, the teams include:

(Which one of the following actions will ensure that Product Backlog items for the Hydrotherapy infrastructure remain aligned with the planned treatment experience throughout development?)

A.

The Infrastructure Team should regularly review and refine Backlog items with Mira Bachar to maintain alignment.

B.

Lock all Backlog items after initial prioritization to prevent scope change and allow the Infrastructure Team to focus on delivering them.

C.

Frequently reassess the priority of Product Backlog items to ensure the Infrastructure Team remain focused on the highest value features.

D.

Encourage the Infrastructure Team to prioritize features for the hydrotherapy treatments since they understand what can be achieved within each Sprint.