Which analysis uses beta and triangular distributions as a tool and technique?

A.

Quantitative risk analysis

B.

Qualitative risk analysis

C.

Perform quality assurance

D.

Perform quality control

When are deliverables accepted or not accepted?

A.

When the project is initiated.

B.

As an output of the scope verification process.

C.

When the project is closing.

D.

In the contract closure process.

The product scope description is used to:

A.

Gain stakeholders' support for the project.

B.

Document the characteristics of the product.

C.

Describe the project in great detail.

D.

Formally authorize the project.

Which of the following is an input to Develop Human Resource Plan?

A.

Team performance assessment

B.

Roles and responsibilities

C.

Staffing management plan

D.

Enterprise environmental factors

You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?

A.

Perform periodic project performance reviews.

B.

Identify quality project standards.

C.

Follow ISO 9000 quality standards

D.

Complete the quality control checklist.

The decision to approve or reject a particular change request is made in which of the following processes?

A.

Perform Integrated Change Control

B.

Monitor and Control Project Work

C.

Develop Project Management Plan

D.

Direct and Manage Project Execution

When managing a project team, what helps to reduce the amount of conflict?

A.

Clear role definition

B.

Negotiation

C.

Risk response planning

D.

Team member replacement

Which of the following provides a basis for assessing project performance?

A.

Profitability and impact matrix

B.

Expert judgment

C.

Benchmarking

D.

Risk categorization

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis

Which of the following outputs from the Schedule Control process aids in the communication of SV, SPI or any performance status to stakeholders?

A.

Performance organizations

B.

Schedule baselines

C.

Performance measurements

D.

Change requests

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?

A.

Risk response planning

B.

Manage stakeholders

C.

Scope definition

D.

Performance reporting

Which type of control tool identifies whether or not a process has a predictable performance?

A.

Cause and effect diagram

B.

Control Charts

C.

Pareto Chart

D.

Histogram

Monitor and control project work is a process of which of the following knowledge areas?

A.

Project risk management

B.

Project scope management

C.

Project time management

D.

Project integration management

Which of the following documents allows the project manager to assess risks that may require near term action?

A.

Probability and impact matrix

B.

Contingency analysis report

C.

Risk urgency assessment

D.

Rolling wave plan

Which one of the following is true regarding the change control board?

A.

Describes how changes are managed.

B.

Approves or rejects change requests.

C.

Needs updated project management plans to approve or reject a change.

D.

Describes how changes are documented.