You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

A.

Schedule

B.

Assumption

C.

Constraint

D.

Planning process

In which type of organization, a project manager is in complete control of the project?

A.

Projectized organization

B.

Balanced Matrix organization

C.

Strong Matrix

D.

Weak Matrix organization

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year?

A.

$600

B.

$1200

C.

$3000

D.

$100

In which type of organization, a project manager is in complete control of the project?

A.

Projectized organization

B.

Balanced Matrix organization

C.

Strong Matrix

D.

Weak Matrix organization

Which of the following plans is not done during the writing of a project plan?

A.

Executive Communication

B.

Risk Management

C.

Quality Management

D.

Scope Statement

When should a project manager be assigned to a project?

A.

As early in the project as feasible.

B.

Preferably before much project planning has been done.

C.

At least prior to the start of project plan execution.

D.

All of the above.

In which phase you define the final deliverable?

A.

Closing

B.

Execution

C.

Planning

D.

Initiation

Which process group is for detailed resource assignments and responsibilities?

A.

Human resources management plan

B.

Project charter

C.

Aplan

D.

Project management plan

A Change Control Board should be _______?

A.

flexible

B.

Include the project manager

C.

appropriate authority

D.

al1 of the above

Market conditions are a part of ________.

A.

Enterprise environmental factors

B.

Project management concerns

C.

Organizational process assets

D.

Cost factor

Which process must occur after a project manager has been assigned to the project?

A.

Collect Requirements

B.

Develop the project charter

C.

Develop the project statement of work

D.

Develop project closing document

Which is not the tools and techniques used in Contract Administration:

A.

Contract change control system

B.

Contract negotiation

C.

Payment system

D.

Performance rating

A Project Cost Management plan is created as a part of:

A.

Develop Project Management Plan process

B.

Control Costs process

C.

Determine Budget process

D.

Estimate Costs process

Which is the most risky phase of a project?

A.

Planning

B.

Closing

C.

Execution

D.

Control

To calculate the late start and late finish dates for a set of tasks , you must do :

A.

An analysis of the critical path

B.

A forwards pass

C.

A backwards pass

D.

a and g