A _______ is a series of actions bringing about a result.

A.

Project plan

B.

Process

C.

Schedule

D.

Flowchart

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

A.

30.0

B.

22.5

C.

25.0

D.

27.5

An example of a project is:

A.

Billing customers

B.

Managing an organization

C.

Constructing a building

D.

Providing technical support

A change requests can occur due to:

A.

An external event such as a change in government regulation.

B.

An error or omission in defining the scope of the product.

C.

An error or omission in defining the scope of the project.

D.

all of the above

Information should be communicated to __________.

A.

Everyone in the communication plan

B.

Everyone on the team

C.

Sponsor

D.

Team 'eacl

Which of the following is ensuring that all features and functions are included in a product or service

A.

Project scope

B.

Project verification

C.

Project control

D.

Product scope

Identification of Mandatory Dependencies is done during which of the following process:

A.

Sequence Activities

B.

Develop Schedule

C.

Define Activities

D.

Estimate Activity Durations

What are the outputs of Initiation process?

A.

Project charter and PM assigned

B.

Constraints

C.

Assumptions

D.

Al1 of the above

The main purpose of project initiation is to ________.

A.

Assign the project manager to the project

B.

Formally describe the project

C.

Produce the project charter

D.

Formally authorize the project

A Risk Register is a part of the ________.

A.

Project Scope Statement

B.

Project Management plan

C.

Project Scheduling plan

D.

Project Charter

Delivery dates and availability of resources can be found in the details of the __________.

A.

Work Breakdown Structure

B.

sow

C.

Project Charter

D.

Project Scope Statement

Which of the following are parts of project scope management?

A.

Verify Scope

B.

Collect Requirements

C.

Control Scope

D.

Al1 of the above

You are the project manager of a project that just went into extinction mode. This means that your project __________.

A.

Has ended before its stated objective

B.

's st'" cunning but missing resources

C.

Will be closed due to lack of resources

D.

None of the above

Function of the __________ is to make sure that changes to anything in the project are recorded and agreed to by the stakeholders.

A.

Project Manager

B.

Sponsor

C.

Team Lead

D.

Management

The project baseline is _______.

A.

Original plans plus the approved changes

B.

Important in the project initiation phase

C.

Initial estimates for tasks and resource utilization

D.

Original plans and the approved major changes