Total 497 questions

While reviewing the data feeds on a project the business analyst (BA) realizes there is a feed that contains complex relationships. In order to help understand the data and accurately reflect a set of requirements the BA decides to prioritize the requirements. What modeling format could the BA use?

A.

User interface

B.

Matrix

C.

Data model

D.

Data dictionary

A business analyst (BA) finds that the solution service level agreement (SLA) cannot be met m one out of five identified scenarios. is there 4 a dependency on a requirement which is a part of a future release. How should the BA approach the solution limitation?

A.

Assess the impact on the business operations

B.

Increase the scope and include the dependent requirement

C.

Modify the SLA

D.

Change the business process

A service provider has seen significant erosion of its profit margin so engages an external consultancy firm to assess its business operations and recommend options to improve profitability. What is the first step that the business analyst (BA) will perform as part of this engagement?

A.

Perform a brainstorming session to determine the desired profit margins for the future state of operations

B.

Organize a requirements elicitation meeting to determine the desired increase in the profit margin

C.

Conduct activities to understand the reasons behind the erosion of profitability in the current state

D.

Hold a strategy session to understand how best to achieve increased profitability

A large insurance company wants to buy a new claims processing system or upgrade one of its two existing system. Each year the claims department is given a $3.5 million budget to spend. Time is of the essence since there are tome regulatory charges that will be coming the following year that will require several features that currently neither one of the two claims System currently support.

There are eight stakeholders involved in this initiative. There are local to where the claim system are managed, while five are located across the country. The business analyst (BA) struggled to get all stakeholders to agree on the desired features but ultimately got agreement on ten identified key features for the new claims system. The BA was able to build a current state and future state process model which included all ten key features.

System a process 75% of the company's claims. It is 5 years old and the claim processors love it because it is easy to use. However, it must go offline for two hours each day. The code is very module so it does have flexibility to be modified. To upgrade system A to have all ten features it would cost $5 million. System A would be at capacity if it were to process all of the company's claims.

System B process 25% of the company's claims. It is an older mainframe system, but rarely goes offline. It could easily handle double the number of claims that system A processes. However, it has a lot of legacy code and would cost $6 million to upgrade.

Both systems have some of the desired key features. But neither system has all ten. The cost to buy a new system would be $7 million.

Below is the estimated cost for each feature in priority order.

If System A is unanimously selected to be the system for upgrade but the technical lead says that System A will have to be taken offline for 3 months, what kind of strategy should the project team develop while system A is offline?

A.

Organizational

B.

Stakeholder

C.

Change

D.

Competitive

In a risk assessment exercise of a software implementation program, the business analyst (BA) has successfully computed the probability of occurrence (POC) and the cost of impact for each of the identified risks as follows:

Which of the following will have the highest negative impact to value?

A.

Natural disasters

B.

Power surges

C.

Human errors

D.

System security

A business analyst (BA) assigned to a project has been asked to implement regulatory requirements based on priority. What type of traceability relationship can the BA use to find an the solution components that need to be implemented?

A.

Satisfy

B.

Dependency

C.

Validate

D.

Derive

An automobile manufacturer is undertaking a project intended to modify or replace the company's current timekeeping system. Negative employee reaction to change follows as word of the proposed solution spreads throughout the company. What could a business analyst (BA) do to prevent or reduce employee discontent?

A.

Record negative employee reaction as a project risk

B.

Propose cultural changes for the organization

C.

Report potential sources of dissent to management

D.

Relay upper management support to stakeholders

A company wants to develop a product roadmap to guide future development efforts. The product owner asks a business analyst IBA) to lead the analysis effort. Feature suggestions have been compiled from customer support calls. Which of the following should the BA do first?

A.

Compare the Implementation costs of each feature

B.

Determine the value of each feature

C.

Prioritize the features in the backlog

D.

Confirm the feature requests

The project manager wants to have the requirements analysis phase approved and asks the business analyst (BA) if this is possible The BA wants to ensure that the requirements package

A.

Solution functional capabilities

B.

Business analysis approach

C.

Solution performance measures

D.

Business analysis information architecture

After having created several prototypes of a new. web-based application, a business analyst (BA) would like to meet with the organization's stakeholders to elicit their perception ideas, and attitudes about the prototypes Which of the following techniques should the SA use?

A.

Decision Analysis

B.

Prioritization

C.

Brainstorming

D.

focus Groups