A business analyst (BA) is measuring solution performance of a new system. What should the BA consider to avoid skewed results and an inaccurate conclusion?

A.

Frequency

B.

Volume

C.

Currency

D.

Timing

A system owner calls the project team to inquire about a recent change in one of the requirements, and insists that the change was never requested. What should the project team do to investigate the issue?

A.

Record a defect for fixing

B.

Consult with the project manager

C.

Revert back the changes

D.

Check the audit history of changes

The business analyst (BA) has prepared a requirements package and it is now ready to present to the stakeholders. What is the purpose of presenting the package?

A.

To document the project's completion

B.

To define the analysis approach

C.

To verity the project's progress

D.

To ensure a shared understanding of the information

A business analyst (BA) is identifying the functions and features required for a new enterprise software solution. The BA reviews historical documents about the current business processes and then interviews each stakeholder group, individually, asking Questions about current business processes. The BA compares the information obtained during the stakeholder interviews with the information gathered from the historical documents. Which activity is the BA performing with this approach?

A.

Verification of requirements

B.

Validation of requirements

C.

Confirmation of elicitation results

D.

Capture of elicitation outcomes

A business analyst (BA) has been spending the majority of the past week cataloguing the new, removed, and modified components of an upcoming project. What is the main purpose of the BA performing this work?

A.

To establish the key performance indicators

B.

To define the future state

C.

To identify the domain subject matter expert

D.

To document the current state

A company is embarking on a software project in a heavily regulated domain. The client expects large upfront planning and detailed documentation for the project. The recommended approach for the project will be:

A.

adaptive.

B.

predictive.

C.

waterfall.

D.

scrum.

A lead business analyst (BA) analyzed the performance of all BA's within the organization. How should the BA approach communicating the results to stakeholders?

A.

Compare a solution used at another company

B.

Identify the performance objectives

C.

Select performance measures

D.

Determine the reporting requirements

The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information about the change. What should the BA review before the meeting?

A.

Minutes from the last steering committee meeting

B.

Organizational structure of the impacted department

C.

Functional design specification of the existing system

D.

Current list of funded initiatives for the current year

A banking giant recently found a major security loophole in their online banking platform that could expose customer information. Security experts and the business analyst (BA) develop a low cost, low effort emergency fix to address this issue. What factor should the BA use to convince the bank to move forward with the emergency fix?

A.

Cost

B.

Schedule

C.

Impact

D.

Urgency

A project to implement shared registration procedures across multiple jurisdictions has stalled several times. The new business analyst (BA) assigned to the project used a collaborative game to elicit requirements. What effect was the BA attempting to achieve?

A.

Minimal variance from planned effort

B.

Close alignment with corporate values

C.

Stimulate teamwork in a fun situation

D.

High confidence in conclusions

Bonny is the business analyst for her organization and she's making a determination from which vendor the solution should be purchased. She has identified several categories to measure each vendor's overall performance and solution. cost, schedule, experience, certification, references, and years in business. For each category, she has identified scores the vendor may earn; for example, cost is worth 25 points, schedule is worth up to 20 points, and years in business is worth up to ten points. The vendor who gets the most points in the assessment will win the contract. What is Bonny using in this scenario?

A.

Scoring model

B.

Vendor profile assessment scale

C.

Weighted scoring model

D.

Screening system

Which basis for prioritization allows the project team to work initially with lower-risk requirements first?

A.

Quantitative ranking

B.

Positive risk ranking

C.

Relationship to other requirements

D.

Implementation difficulty

Enterprise analysis creates just five outputs. Which one of the following is an output of the enterprise analysis tasks?

A.

Stakeholder concerns

B.

Solution approach

C.

Solution performance assessment

D.

Assumptions and constraints

In order to plan business analysis activities, you will need four inputs. Which one of the following inputs is not valid for this task?

A.

Business analysis approach

B.

Stakeholder tolerance for risk

C.

Stakeholder list, roles, and responsibilities

D.

Business analysis performance assessment

Which approach is best to take when a business analyst is assessing the solution options for a business need when there are relatively few criteria involved?

A.

Focus on the life cycle costs of the solutions.

B.

Focus on the commonalities of the solutions.

C.

Focus on the differences of the solutions.

D.

Focus on the implementation cost of the solutions.