The process of defining the business need uses one output. What is it?
Henry is meeting with Janet, the business analyst of the organization. They are discussing an opportunity to create a new service their company can provide, though the startup of the service would take time and an investment. Henry wants Janet to explore the possibility of this new venture. What activity is Henry asking Janet to complete?
Henry is a business analyst in his organization and he's asked an expert to help him determine the best business analysis duties to implement. Why would Henry ask an expert to help him define the business analysis duties?
When a business analyst assists in the planning of the solution implementation, she must always consider the constraints for implementation. Which one of the following cannot be considered as an implementation constraint?
Complete this sentence in regard to the level of abstraction. Requirements need to sayneeds to be done, notto do it.
One of the techniques to assess capabilities in an organization is to use SWOT. What does SWOT accomplish?
Which one of the following statements best describes the purpose of allocating requirements?
Which of the following are not appropriate for a plan-driven business analysis approach? Each correct answer represents a complete solution.
There are four methods to generate the business need in an organization. Which approach is described as the need to achieve a strategic goal?
Beth is a business analyst for her organization and she's completing the tasks in the requirements management and communication knowledge area. As a result of these tasks, she'll create several things for her organization. Which one of the following, however, is not one of the outputs of the requirements management and communication tasks?
Which of the following defines all of the required work to satisfy the requirements of the project?
A business analyst (BA) has completed an impact analysis of a proposed change, gained approval for the change, and has updated the requirements. The project sponsor wants to be updated with an overview of the results. How should the BA communicate the results?
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?
When a business analyst is using alternative generation, what should she always include as an output?
As a business analyst, you need to define when the activities of the business analysis approach will take place. This includes all of the following business analysis approach activities except for which one?