Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

FIDIC CCM - Certified Contract Manager

Page: 4 / 5
Total 140 questions

When does discharge become effective under the FIDIC Red Book (edition 1999)? (1 correct answer applies)

A.

When the Contractor receives full payment certified through the Final Payment Certificate.

B.

When the Contractor receives its Performance Security from the Employer.

C.

When the Contractor receives full payment certified through the Final Payment Certificate and return of the Performance Security.

D.

When the Employer counter signs a discharge notice as issued by the Contractor, following full payment and return of the Performance Security.

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).

A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.

B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.

C.

The appointment of the Contractor ' s Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.

D.

Receipt of a statement and supporting documents.

The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

A.

The Commencement Date

B.

The date of the Taking Over Certificate

C.

The date on which the entire advance payment is repaid as stated in the Payment Certificate

D.

The date on which an amount is repaid by the Contractor as stated in the Payment Certificates

You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.

The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.

1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.

The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.

What is the correct Commencement Date?

A.

12 June 2022

B.

15 June 2022

C.

15 July 2022

D.

1 August 2022

Which one of the following statements is NOT correct in respect of FIDIC Red Book (both editions)?

A.

The Letter of Tender may be worded by the Contractor (at its discretion) so as to allow for the alternative of the Contract to become effective when the Employer issues a Letter of Acceptance.

B.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

C.

The Contract is administered by the Engineer who is appointed by the Employer. If disputes arise, they are referred to a Dispute Adjudication Board (DAB) for its decisions.

D.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?

A.

True

B.

False

(You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))

A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.

Under the FIDIC Construction Contract, which one of the following statements is correct?

A.

Payments of a DAB Member ' s retainer fee is the sole responsibility of the Contractor.

B.

For an ad-hoc DAB, a retainer fee for each DAB Member must be paid to the Member on the first day of each calendar month.

C.

Payment to DAB Members must be certified by the Employer.

D.

If all persons nominated to serve as members of an ad hoc DAB do not sign a DAB Agreement, an appointing entity can make appointments.

E.

A DAB must give its decision in writing on any dispute when requested by one of the Parties.

You are the Contract Manager of the Engineer in a hotel project. In May 2020, the Employer and the Contractor signed a Contract based on the FIDIC Yellow Book (edition 2017), as per which the Contractor will design and build a hotel project with Contract Price of 5,100,000 USD. The Time for Completion for this project is 12 months (May 2021). The Contract also named a nominated Subcontractor (as referred to in Sub-Clause 4.5) who provides mechanical, electrical, and plumbing services for the project (including the fire fighting system), which was accepted by the Contractor without any discussions.

The Project was delayed due to issues with the fire fighting system, and you issued the Taking-Over Certificate in June 2022.

The Employer sent a Notice of Claim to the Contractor on Delay Damages with a maximum value equal to 10% of Contract Price (510,000 USD). The Employer also gave a Notice to the Contractor stating that the Contractor has failed to submit the evidence of payment to the nominated Subcontractor as well as the reason for withholding payment to the nominated Subcontractor. Therefore, the Employer has paid the nominated Subcontractor directly the entire amount due, coming to 100,000 USD. The Employer intends to include this amount as a deduction in the Final Payment to the Contractor.

As Contract Manager of the Engineer, you are tasked to make a fair determination of the Notices of the Employer. In your " Notice of the Engineer ' s determination " , what is your determination for the deduction of the next Interim Payment to the Contractor in relation to the amount directly paid to the nominated Subcontractor?

A.

The Employer is entitled to deduct the amount directly paid.

B.

The Employer is not entitled to deduct the amount directly paid.

In a drafted FIDIC Silver Book (edition 1999), the following sentence has been added to Sub-Clause 3.5:

" In case of an Instruction regarding a pending or proposed Variation, Contractor shall carry out any determination regardless of a possible notice of dissatisfaction. "

What GP(s) is/are breached?

A.

GP1 only

B.

GP3 only

C.

GP1 and GP3

D.

GP1, GP2 and GP3