When developing a strategy to engage stakeholders, what level of engagement should be the goal of the strategy?

A.

Highest among senior stakeholder groups and lowest among front-line stakeholder groups

B.

Uniform across all stakeholder groups

C.

Uniform among internal stakeholder groups and among external stakeholder groups

D.

The level of engagement will depend on what each stakeholder group needs to know and do in the change

What are three main components you should include in a communications plan?

A.

Frequency of communication, RACI and communication strategy

B.

Target audience, key messages and desired outcomes

C.

Cost and resourcing, measures of success and monitoring feedback

D.

Communication channels, stakeholder analysis and learning and development plan

Who should be involved to ensure the credibility of measuring change achievements?

A.

The most charismatic leader in the organization

B.

Someone from the impacted business unit

C.

The stakeholder with the highest risk

D.

The sponsor with the highest formal role

A new change initiative is being planned at an organization. Efforts are made by the change management lead to outline the case for change including the current opportunities, risks, consequences of the change, and the benefits of the change and how it aligns to the organization’s strategic priorities. What is the next key action to be taken?

A.

Determine why the change is required

B.

Develop the change charter

C.

Develop a clear vision of the future state

D.

Identify goals, objectives and success criteria

Which planning document includes activities designed to drive the behavior of those impacted by a change initiative?

A.

Stakeholder engagement plan

B.

Sponsorship plan

C.

Transition plan

D.

Resource plan

A change in leadership resulted in a need to adjust an existing change management plan. To maintain momentum, what needs to happen after these adjustments are approved?

A.

A person is identified to respond to questions about the adjustment

B.

Decisions are communicated to governing bodies only

C.

Decisions are communicated to all relevant stakeholders

D.

Original plans are immediately deleted

What document should provide guidance and best practices for future change initiatives?

A.

Risk log

B.

Project charter

C.

Change management plan

D.

Lessons learned evaluation

What document explains the current opportunity, risks or consequences and benefits of a change?

A.

Change research

B.

Success measures

C.

Change definition

D.

Business case

During the execution phase, what can a change manager do to ensure the most effective use of people?

A.

Integrate human resources with the change to give input on how to execute

B.

Implement a controlled spending request and approval process

C.

Establish a process to monitor physical resources and their performance

D.

Implement a process for creating, storing, and sharing documents and reports

Which plan is used to document continuous improvement steps such as implementing tasks based on feedback and observations?

A.

Sustainability plan

B.

Learning and development plan

C.

Measurement and benefits realization plan

D.

Stakeholder engagement plan