Which task in change management defines the approach, scope, roles and responsibilities in undertaking detailed impact analysis and readiness planning for implementing the change?

A.

Stakeholder engagement strategy

B.

Develop the measurement and benefit realization strategy

C.

Develop the change impact and readiness strategy

D.

Develop the learning and development strategy

You are currently leading a major ongoing change initiative. You observe that the project lacks support, lacks active engagement in the change effort and loses interest in the change effort. Under the circumstances, what would be the best strategy to address this constraint and enable an intervention to happen?

A.

The risk management and intervention strategy

B.

The change strategy

C.

The stakeholder strategy

D.

The communication strategy

You are developing the communications strategy and as part of the process are considering who will deliver specific messages to employees. One of the key messages you wish to be delivered is the “What’s in it for me” from the employees’ perspective. Who should be the preferred sender of this message?

A.

Human resources representative

B.

Employees’ supervisor

C.

Change management team leader

D.

Executive manager

What is the intended outcome of a measurement and benefits realization plan?

A.

Measure stakeholder commitment and sponsor satisfaction

B.

Identify when change effort is not meeting goals and mitigation strategies are required

C.

Identify when a change effort is meeting goals and rewards are appropriate

D.

Measure when a change effort has achieved desired adoption levels

The change project aims at growing market shares for division X. Over the past weeks customers have been indicating that they are not ready for the new product line. What do you need to do to decrease the speed of change?

A.

Modify the feedback mechanism

B.

Modify the organizational readiness assessment

C.

Modify the change management plan execution

D.

Modify the measurement plan

A state-owned company engaged in a change project faced a major issue related to its image as a socially responsible organization. What could the leaders do to ensure the outcomes remain consistent with the company vision?

A.

Make adjustments to the change management plan by adding, eliminating, or realigning change program components to reinforce the change

B.

Take action to ensure stakeholders don’t retreat to the prior current state condition

C.

Leverage the communication plan to ensure that it supports the big picture of where the organization’s strategic priorities are

D.

Observe and objectively measure sustained behaviors and attitudes throughout the process

Who is responsible for coordinating, applying and tracking change management activities?

A.

Change management lead

B.

Change stakeholder

C.

Sponsor

D.

Change agent

What document addresses closing the competency gap?

A.

Learning and development strategy

B.

Stakeholder engagement strategy

C.

Change impact and readiness strategy

D.

Communications strategy

As the project reaches completion, whose approval should be sought to formally close the change?

A.

Senior sponsor

B.

Project manager

C.

Change Lead

D.

Training Lead

An organizational design project involving the restructuring of the sales force has just gotten underway and the change management lead is planning where (s)he can apply the recently completed stakeholder analysis assessment. What set of plans would a stakeholder analysis be used to develop?

A.

Stakeholder engagement plan, communication plan and training plan

B.

Resistance management plan, coaching plan and training plan

C.

Sponsorship plan, coaching plan, and training plan

D.

Sponsorship plan, communication plan and training plan