Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

AACE International CCP - Certified Cost Professional (CCP) Exam

Page: 5 / 6
Total 189 questions

AACE International defines _____________as a technique of economic evaluation that sums over a given study period, the costs of initial investment, replacements, operations, and maintenance/repair; expressed in either present or annual value terms.

A.

Risk analysis

B.

Benefit/Cost ratio (B/C) method

C.

Net present worth method

D.

Life cycle costs method (LCC)

The process of stating goals and determining the most effective way of reaching them is the definition for:

A.

Implementing

B.

Mission Statement

C.

Managing

D.

Planning

In the application of the benefit/cost method of analysis, what are the criteria for determining whether a proposed project is acceptable?

A.

B/C is - 1.0

B.

B/C is <1.0

C.

B/C is > minimum ROR

D.

B/C is >1.0

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

It S480 is the target net profit, then the total sales volume (in dollars) is:

A.

$30,000

B.

$37,500

C.

$34,400

D.

$32,400

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

A.

4.62

B.

4.24

C.

4.10

D.

4.31

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Given a unit price contract between the owner and contractor, each assumes the following:

A.

Bid unit rate, owner quantities can exceed estimate range Contractor can perform above

B.

Bid unit rate, owner quantities are within estimate range

C.

Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range

D.

Contractor can perform at or below bid unit rate, owner quantities are within estimate range

What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.

A.

Engineer

B.

Alternate

C.

Project Manager

D.

Agent

If a project is said to be on a "fast track program/' the fast track method is:

A.

Simultaneous working engineering, procurement, and construction, with appropriate overlap from each phase of work so that delays are eliminated and all the work is streamlined into a correct plan of logic/sequence and duration for all of the work

B.

First completing engineering and procurement, then executing construction

C.

Analyzing the project and specifying the basic approach to be used in its execution; segmenting the project into reasonable number of activities; estimating the time required to perform each activity; placing the activities in time order, considering both sequential and parallel performance

D.

Revising the schedule logic to make it possible to identify constraints of faulty logic; revising the durations in the n p schedule that have been based on assumptions regarding the \hay the work would be performed; revise the resources to work multiple shifts; evaluate the use of overtime

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

What is the schedule variance (SV)?

A.

BCWS - BCWP = 100.000 – 105,000 = -5,000

B.

ACWP - BCWS = 110.000 – 100,000 = 10,000

C.

BCWS -ACWP = 100.000 – 110,000 - -10,000

D.

BCWP - BCWS = 105.000 - 100.000 =- 5,000

refers to the process of calculating and reporting the non-monetary functions of the strategic asset portfolio.

A.

Asset performance assessment

B.

Asset project reporting

C.

Asset investment decision and funding

D.

Asset performance measurement