Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

AIChE CCPSC - CCPS Process Safety Professional Certification

Page: 2 / 4
Total 110 questions

A process calls for the addition of a reactant over a certain period of time. The flow controller on the reactant’s feed line was out of calibration and reduced the flow rate of the reactant. The operator noticed the addition rate was too low and, contrary to the operating procedures, he opened a bypass valve around the flow control valve to increase the flow rate. As a result, the operator added the remaining reactant too quickly, and a runaway reaction occurred. Weaknesses in which of the following Risk Based Process Safety elements could have contributed to the cause of this incident? (Select all that apply)

A.

Asset Integrity and Reliability

B.

Conduct of Operations

C.

Workforce Involvement

D.

Training and Performance Assurance

E.

Incident Investigation

What minimum size is normally used for laboratory test apparatus to determine dust explosion severity?

A.

5 liters

B.

1 cubic meter

C.

20 liters

D.

50 liters

Which of the following events require a process safety incident investigation? (Select all that apply)

A.

Explosion

B.

Fire in an office building

C.

Toxic release

D.

Allergic response

E.

Runaway reaction

F.

Slip, trip, or fall injury

Process Safety Competency is not involved with succession planning. True or False?

A.

True

B.

False

After an incident with fatal consequences, you are requested by top management to form an investigation team. Who of the following would be the most suitable candidate to lead the company investigation?

A.

The plant manager

B.

The integrity and maintenance supervisor

C.

The lead process engineer of the plant

D.

An authorized off-site company resource

E.

A representative of the contractor that was performing the task when the accident occurred

When should worker refresher training be done? (select all that apply)

A.

When production schedules permit

B.

When training is required by law or regulation

C.

When there is a gap between a worker’s knowledge and the knowledge needed to do a job

D.

After the Process Safety program audit

E.

Before implementation of a process change

Consider the information shown on the diagram. Which Risk Based Process Safety elements are most relevant to this situation? (select all that apply)

A.

Auditing

B.

Hazard Identification and Risk Analysis

C.

Emergency Management

D.

Contractor Management

E.

Stakeholder Outreach

F.

Safe Work Practices

What are the main objectives for conducting a Process Safety Management audit? (Select all that apply)

A.

Reduce process safety risks

B.

Verify effectiveness of Risk-Based Process Safety management systems

C.

Identify program improvement opportunities

D.

Prepare an emergency response plan

E.

Certify that all Operating Procedures are correct and up-to-date

A worker appears to be improvising instead of following procedures. A review indicates that the procedures provide the correct instructions. The worker says “I don’t understand the procedure, can you explain?” You explain the procedure, and then this worker performs consistently well. Then you give the worker a new procedure to follow and this worker begins to improvise on the new procedure. After a verbal explanation the performance improves. What is the most likely explanation for this situation?

A.

Worker does not understand what can go wrong if procedures are not followed

B.

Worker did not study new procedures before using them

C.

Worker may have a reading disability

Which of the following statements are correct regarding the flow control loop in the illustration? (Select all that apply)

A.

The component failure probabilities are multiplied together to determine the overall failure probability for the control loop.

B.

The component reliabilities are multiplied together to determine the overall reliability for the control loop.

C.

The overall failure of the control loop requires failure of all of the components.

D.

The overall failure of the control loop requires failure of only one of the components.