In a make-to-order (MTO) environment, inputs to sales and operations planning (S&0P) should include the:

A.

projected backlog of customer orders.

B.

work-in-process (WIP) inventory.

C.

finished goods inventory.

D.

available-to-promise (ATP) data.

Which of the following activities would be effective to mitigate the bullwhip effect?

A.

Implement track and trace technology.

B.

Use a push system.

C.

Reduce lead times.

D.

Increase inventory.

A company can easily change its workforce, but inventory carrying costs are high. Which of the followingstrategies would bemost appropriate during times of highly fluctuating demand?

A.

Produce to backorders

B.

Produce at a constant level

C.

Produce to the sales forecast

D.

Produce to demand

Which of the following tools is used to evaluate the impact that a production plan has on capacity?

A.

Demand time fence (DTF)

B.

Bill of resources

C.

Product routing

D.

Safety capacity

Fishbone diagrams would help a service organization determine:

A.

the proper level of service for a customer segment.

B.

the source of aquality-of-serviceissue.

C.

differences in the performance of employees.

D.

the decomposition of customer return rates with seasonality.

A reduction in purchased lot sizes will reduce which of the following items?

A.

Inventory levels

B.

Frequency of orders

C.

Reorder points (ROPs)

D.

Setup times

External sustainability reporting and verification is an opportunity for a company to communicate its:

A.

confidence.

B.

profitability.

C.

growth.

D.

performance.

A customer requests an order of 100 units in Period 1. The master schedule for the item indicates an available-to-promise

(ATP) of 85 units for Period 1. Which of the following approaches is the most appropriate course of action?

A.

Increase the master production schedule (MPS) quantity in Period 1 by 15 units.

B.

Promise the 100 units, and then check on component availability.

C.

Promise the 85 units in Period 1 and the remaining 15 units in the next possible ATP period.

D.

Promise the 100 units by removing 15 units from another customer's order with a smaller revenue value.

Given the information below, reducing which measure by 10% would contribute most to shortening the cash-to-cash cycletime?

A.

Accounts receivable

B.

Inventory value

C.

Accounts payable

D.

Cost of capital

An order that moves into a work center on schedule following completion of a previous operation will move:

A.

to the end of the queue.

B.

to the beginning of the queue.

C.

into the queue in priority sequence.

D.

into the queue when there is capacity available.