You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
Select which option best completes the following statement: _____________ is all about response to change.
Who defines the Sprint Backlog scope?
The most encouraged time of day to hold a Scrum Daily Meeting is:
Who is on the Scrum Team?
The _____________ Team is responsible for delivering potentially shippable product increments at the end of each Sprint.
How should items in the Product Backlog be ordered?
Which three activities will a Product Owner likely engage in during a Sprint?
The correct sequence of events in using Scrum framework is as follows: