Which of the following statements about the testing quadrants is true?

A.

The higher the number of the testing quadrant, the more important the tests associated with this quadrant are

B.

Automated acceptance tests produced during BDD and ATDD are classified in quadrant Q2

C.

Exploratory tests are classified in quadrant Q3. and they are usually included in a continuous integration process

D.

Automated unit tests produced during TDD are classified in quadrant Q4 as they are technology facing

A software development company invests heavily in tools to support the entire software development lifecycle, including testing. They have a tool that allows automated creation and installation of builds and subsequent execution of various types of automated tests. Which ONE of the following is a CORRECT statement about this type of test tool?

A.

It is an example of collaboration tool

B.

It is an example of DevOps related tools

C.

It is an example of automated unit testing tool

D.

It is an example of test implementation tool

Which ONE of the following roles is responsible for mediating, managing time, and generating a safe review environment in which everyone can speak freely?

A.

Manager

B.

Reviewer

C.

Review leader

D.

Moderator

Which of the following statements about static testing and dynamic testing is true?

A.

Unlike dynamic testing, which can be also performed manually, static testing cannot be performed without specialized tools

B.

Static testing is usually much less cost-effective than dynamic testing

C.

Unlike dynamic testing, which focuses on detecting potential defects, static testing focuses on detecting failures which may be due to actual defects

D.

Both static testing and dynamic testing can be used to highlight issues associated with non-functional characteristics

Which ONE of the following elements is TYPICALLY part of the test plan?

A.

The budget and schedule for the test project.

B.

A detailed report on the test results after the test project is completed.

C.

A list of test logs from the test execution.

D.

A detailed analysis of the defects found and their causes.

Which of the following statement about the shift-left approach is false?

A.

The shift-left approach can only be implemented with test automation

B.

The shift-left approach in testing is compatible with DevOps practices

C.

The shift-left approach can involve security vulnerabilities

D.

The shift-left approach can be supported by static analysis tools

Which of the following is a task the Author is responsible for, as part of a typical formal review?

A.

Determining the people who will be involved in the review

B.

Recording the anomalies found during the review meeting

C.

Identifying potential anomalies in the work product under review

D.

Fixing the anomalies found in the work product under review

In addition to thorough testing of the requirements specification, a development team aims to involve users as early as possible in the development process, using practices such as prototyping, to ensure that the software systems being developed will meet the users’ expectations. This approach is especially useful at mitigating the risks associated with one of the seven testing principles, which one?

A.

Tests wear out

B.

Absence-of-errors fallacy

C.

Working software over comprehensive documentation

D.

Defects cluster together

Which of the following is a factor that contributes to a successful review?

A.

All participants to the review will be evaluated based on the defects they will find

B.

The author of the work product to be reviewed leads the review meeting

C.

All participants to the review are trained to deal with the review type and its objectives

D.

Review metrics must be collected to improve the review process

Which of the following statements is not correct?

A.

Looking for defects in a system may require Ignoring system details

B.

Identifying defects may be perceived as criticism against product

C.

Looking for defects in system requires professional pessimism and curiosity

D.

Testing is often seen as a destructive activity instead of constructive activity