SAP C_S43_2022 - SAP Certified Application Associate - SAP S/4HANA Asset Management

Page: 2 / 3
Total 80 questions

The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100% which date is relevant for the calculation of future planned dates if the maintenance work is delayed?

A.

Planned date of the next call, independent of maintenance order dates

B.

Actual finish date of the maintenance order

C.

The date of the final confirmation

D.

Technical completion date of the maintenance order

Where can you see the results of the material availability check for maintenance orders? Note: There are 2 correct answers to this question

A.

Within a maintenance order

B.

In the list editing (single-level) for maintenance orders

C.

In the report Material: Where-Used List

D.

In the material reservation list in inventory management

You want to assign components to a General Maintenance Task List. What are prerequisites for assigning material components to a task list operation? Note: There are 2 correct answers to this question

A.

Assign the header material of a material BOM as assembly to a task list operation.

B.

Assign the BOM usage for free assignment of material in Customizing

C.

Assign the header material of a material ROM to the assembly field of the task list header

D.

Assign a piece of equipment with allocated material BOM to a task list operation.

What are mandatory characteristics of orders with Operation Account Assignment (OAA)? Note: There are 3 correct answers to this question

A.

Overall costs are dynamically summed up on the header level.

B.

A technical object must be assigned to an order operation

C.

Costs are stored only for the operation object

D.

Purchase requisitions have the operation as account assignment.

E.

The settlement rule is maintained on the header level.

Which of the following parameters are available when you define a new maintenance plan category? Note: There are 3 correct answers to this question.

A.

Completion data

B.

Maintenance activity type

C.

Call object

D.

Change documents

E.

Order type

Which default object type do you use to settle a refurbishment order?

A.

The cost center

B.

The WBS element

C.

The fixed asset

D.

The material

You want to implement SAPUI5 apps in your SAP Fiori Launchpad. Which are mandatory elements? Note. There are 2 correct answers to this question?

A.

Web Dynpro Apps

B.

Transactions

C.

Catalogs

D.

Tile Groups

How does a maintenance request within the phase-based process differ from a maintenance notification in the standard process?

A.

It always uses the risk-based assessment for prioritization.

B.

It is a new business object with no connection to a maintenance notification.

C.

It is mandatory to assign a task list to the maintenance request.

D.

It contains an additional screening phase where requests can be accepted or rejected.

You cancel the technical completion of a work order. What are the effects? Note: There are 2 correct answers to this question?

A.

Open reservations are recompiled.

B.

Open purchase requisitions are recompiled

C.

Referenced notifications are put in Process again.

D.

Open purchase orders are recompiled.

How is Phase-based Maintenance Processing activated in the SAP system? Note: There are 2 correct answers to this question

A.

Through Best Practices scope items 4HH and 4HI.

B.

Phase-based maintenance is always active in all S/4HANA 2021 editions and above

C.

By installing the corresponding enhancement pack and activating the related business function

D.

By manually activating the corresponding Business Feature in case Best Practices are not used.