Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

EMC D-PEXE-IN-A-00 - Dell PowerEdge XE9680 and XE8640 Install

Page: 1 / 1
Total 14 questions

A deployment engineer is installing eight PowerEdge XE9680 servers. Two servers will be installed in each of four racks. The data center managers must plan for the power needed to supply power to

the four racks.

What power consumption information can the deployment engineer give the data center manager?

A.

Each rack must have at least 6 PDUs for power high availability.

B.

Each server has four 2800-Watt, 15.6 Amp PSUs.

C.

Each rack must power 12, 2800-Watt, 15.6 Amp PSUs.

D.

Each PDU must use a C20-type connection.

A deployment engineer is installing an XE9680 server. The network connectivity has 24 optical cables that route to switches in the data center. The administrator questions the use of a cablemanagement arm (CMA).

What are two items to consider when installing a CMA?

A.

The CMA can be installed to open on either the left or right side of the server.

B.

Do not route optical cables through the CMA.

C.

A CMA can only be installed with a strain relief bar.

D.

The XE9680 does not support a CMA.

A deployment engineer goes on-site to install a mix of XE systems in a customer testing and development data center. The customer engineering group is stress testing the PowerEdge XE servers to

determine the best XE server for their software applications. As one of the first steps, they must ensure the correct server rails are on-site.

Which three options are a correct matching of rail type with server type?

A.

XE9640 and B27

B.

XE9680 and B25

C.

XE9640 and B25

D.

XE8640 and B27

E.

XE9680 and B28

A deployment engineer is installing a PowerEdge XE8640 server. The server is on a lift, and they have aligned the server inner rails with the rail assemble that are secured in the rack. The engineer

can only push the server into the rack a short distance before it stops. Pushing forcefully causes the rack to slide back.

What action should the deployment engineer take?

A.

Press the mechanism on the rail to release the rail lock.

B.

Lower the lift and move away from the server.

C.

Pull the server out of the rack and realign the lift with the rack.

D.

Have a person hold the rack while using force to slide in the server.