You work as a project manager for PassGuide Inc. You are concerned with defining and controlling what is or is not included in the project. Which of the following processes will you use to accomplish the above task?

A.

Project scope management

B.

Risk management

C.

Project communications management

D.

Project reporting structure

You have been assigned as the Project Manager for a new project that involves development of a new interface for your existing time management system. You know that developers are available in your organization, and would like to use them. However, your program manager thinks that an outside company needs to be engaged to complete this development. Which of the following will help you to convince your project manager to use the internal resources?

A.

Expert Judgment

B.

Make or buy analysis

C.

Survey Questionnaire

D.

Issue log

You are the project manager of the UTN Project and are working on the roles and responsibilities for your project. You'll need to define four aspects of the roles and responsibilities. All of the following must be defined except for which one?

A.

Management

B.

Competency

C.

Role

D.

Responsibilities

Mark works as a project manager for PassGuide Inc. You have to monitor the status of the project and product scope. Which of the following processes will you use to accomplish the task?

A.

Create WBS

B.

Define Scope

C.

Verify Scope

D.

Control Scope

You work as a project manager for PassGuide Inc. You are working on a construction project. You are compiling and reviewing the comments to draft deliverables prior to forwarding them to the contractor for incorporation into the final draft. You are responsible for communicating the changes to the reviewer who initially made the comments. Who among the following will be responsible for updating the draft deliverables and producing the final deliverables in the above scenario?

A.

Contractor

B.

Project manager

C.

Reviewer

D.

Risk manager

The figure given below demonstrates the communication model for a project. What role does the component D play in the communication model?

A.

Transporter

B.

Sender

C.

Medium

D.

Encoder

You work as a project manager for PassGuide Inc. You are performing a task to generate a hierarchical list of resources related by function and resource type that is used to facilitate planning and controlling of project work. Which of the following components of project management will you use to accomplish the above task?

A.

PERT chart

B.

WBS

C.

RBS

D.

Gantt chart

Which of the following are inputs of the Control Scope process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Project management plan

B.

Work performance information

C.

Change request

D.

Requirements documentation

Which of the following does not require the WBS as an input?

A.

Activity definition

B.

Cost estimating

C.

Negotiation

D.

Resource planning

What component of the change control process examines the entire project to determine the proposed change's impact on the project scope, time, cost, quality, human resources, communications, risk, and procurement?

A.

Integrated change control

B.

Scope change control system

C.

Configuration management

D.

Project management information management system