Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

GIAC GCPM - GIAC Certified Project Manager Certification Practice Test

Page: 7 / 12
Total 397 questions

In which of the following process groups is the initial scope defined and are the initial finances committed?

A.

Executing

B.

Monitoring and controlling

C.

Initiation

D.

Planning

Which of the following are outputs of the Develop Project Team process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Team performance assessment

B.

Project management plan

C.

Enterprise environmental factors update

D.

Project staff assignment

What is the smallest element in a WBS called?

A.

Deliverable

B.

Work package

C.

Resource

D.

Assignment

Which of the following are the prime reasons behind the use of the Critical path method in a project?

Each correct answer represents a complete solution. Choose all that apply.

A.

It categorizes the tasks that can be delayed for a while if resources need to be reallocated to catch up on missed tasks.

B.

It determines both the early start and the late start date for each activity in the schedule.

C.

It identifies the tasks that should be completed on time for the whole project to be completed on time.

D.

It is used to describe the maximum length of time needed to complete a project.

Which of the following are inputs of the Direct and Manage Project Execution process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Organizational process assets

B.

Approved change requests

C.

Quality metrics

D.

Project management plan

Tom works as the project manager for BlueWell Inc. He spends the majority of his time communicating with team members and the project stakeholders. Various communication skills are involved in the communication processes. Which communication skills are involved in this process?

Each correct answer represents a part of the solution. Choose all that apply.

A.

Formal and Informal

B.

Vertical and Horizontal

C.

Internal and External

D.

Confronting and problem solving

Which of the following best describes the identification, analysis, and ranking of risks?

A.

Fixed-price contracts

B.

Plan Risk management

C.

Fast tracking

D.

Design of experiments

Robert is the project manager of the NHH Project and is working with his project team to create the WBS for his organization. He has a project scope statement that needs to be broken down into smaller, more manageable components. He would like to organize the components by project phase to help organize the deliverables created in each phase of the project. What is the tool and technique called that breaks down the project scope into the WBS?

A.

Decomposition

B.

Requirements breakdown

C.

Functional analysis

D.

Subdivision

Which of the following are outputs of the Acquire Project Team process?

Each correct answer represents a complete solution. Choose all that apply.

A.

Organizational process assets

B.

Project staff assignments

C.

Resource calendars

D.

Project management plan updates

Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?

A.

Project communications plan

B.

Project management plan

C.

Project contractual relationship with the vendor

D.

Project scope statement