Pre-Winter Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PECB ISO-9001-Lead-Auditor - QMS ISO 9001:2015 Lead Auditor Exam

Page: 3 / 8
Total 267 questions

You are conducting a Stage 1 audit at an organisation that services refrigeration equipment for a large customer base. The scope of certification is “Provision of refrigeration equipment maintenance and repair services”. You are interviewing the Managing Director to learn more about the organisation and to explore how the requirements for policy, objectives, and risks and opportunities in ISO 9001 are addressed.

The Managing Director explains that they only use sub-contract refrigeration engineers and do not have any full-time refrigeration engineers, which helps to optimise overhead costs. The full-time staff employed are essentially a small team of office staff who process customer enquiries, schedule jobs and process invoices.

The Managing Director adds that the ISO 9001 requirements for competence of personnel extends to both sub-contract and full-time staff. He also states that the full-time staff are aware of the Quality Policy, objectives and plans to address risk and opportunities.

You ask if the sub-contract engineers have been informed of the Quality Policy, objectives and plans to address risks and opportunities, to which the Managing Director replies that this is not applicable as they only use sub-contractors who operate ISO 9001 certificated quality management systems. The documented information provided to the auditor confirms this.

Which clause in ISO 9001 is most likely not to have been fulfilled in this instance?

A.

7.4 Communication

B.

7.3 Awareness

C.

7.2 Competence

D.

7.5 Documented information

What does the application of the process approach in a QMS enable?

A.

The improvement of processes based on the needs and expectations of interested parties

B.

The consideration of processes in terms of financial value

C.

The achievement of effective process performance

D.

The reduction of resource consumption

One of the conflict resolution techniques is toning down. How is the conflict managed in that case?

A.

Following negotiations, each party makes concessions in order to reach a common agreement.

B.

The audit team leader uses their authority to solve the conflict.

C.

The points of agreement are emphasized and the points of disagreement are put into perspective.

According to ISO 19011, what two activities take place during the conduct of a audit follow-up?

A.

Verify the effectiveness of the implemented corrective actions

B.

Verify corrections taken to fix the reported non-conformities

C.

Verify legal compliance

D.

Plan the next audit

E.

Determine feasibility of the audit

F.

Assign roles and responsibilities of observers

Select the word that best completes the sentence:

Scenario 7: POLKA is a car manufacturing company based in Stockholm, Sweden. The company has around 14,000 employees working in different sectors which help with the design, painting, assembling, and test drives of the final product. The company is widely known for its qualitative products and affordable prices. In order to retain their reputation, POLKA implemented a quality management system (QMS) based on ISO 9001.

Before applying for certification, the company decided to conduct an internal audit to check whether there are any nonconformities in their QMS and if the requirements of ISO 9001 are being fulfilled. The top management appointed Sean, the internal auditor, as the team leader of the internal audit team. Sean required from the top management to have unrestricted access to the employees and executives of POLKA and to the documented information. Furthermore, Sean required to establish a team with a large number of auditors, considering the size and the complexity of the organization. The top management of POLKA agreed with Sean ' s requirements.

The top management, in cooperation with Sean, assigned 10 more employees to the audit team. Following that. Sean planned the audit activities and assigned the roles and responsibilities to each auditor. They began by interviewing employees of different manufacturing departments to check whether they are aware of the process of the QMS implementation. While conducting these activities, one of the auditors asked Sean for permission to audit the department in which he worked on a daily basis, as he was very familiar with the processes of the department.

Along the way, the teams findings showed that the staff were trained, documented information was updated, and the QMS fulfilled the requirements of ISO 9001. The internal audit took three weeks to complete, and on the last week the audit team held a final meeting

The team shared their results and together drafted the audit report This report was submitted to the top management of the company. The report was maintained as documented information, and was available to the relevant interested parties.

Based on the scenario above, answer the following question:

Based on Scenario 7, the team worked together to draft the final audit report. Is this acceptable?

A.

Yes, audit team members should contribute to drafting one general report for the findings and conclusions

B.

No, audit team members should draft separate reports for their findings and conclusions

C.

No, it is the responsibility of the audit team leader to draft the audit report

Which of the options below is an example of minor nonconformity?

A.

Some of the nonconformities were not closed as planned (on time) and no justification was provided or documented

B.

Lack of commitment from the top management

C.

Lack of corrective actions to address recurrent incidents

What must the auditor consider in order to mitigate audit risks and obtain reasonable assurance?

A.

The processes deemed material to the auditee.

B.

The needs and expectations of internal interested parties.

C.

The previous audit results.

D.

The financial risks associated with QMS implementation.

In the context of a third-party audit, select the issue which is not expected to be included in the audit plan.

A.

Number of sites to be audited

B.

Risk to achieving audit objectives

C.

Expectations of the organisation ' s management

D.

Scope of the audit

You are preparing an audit plan for a third-party ISO 9001 audit of organisation ABC that extracts lithium from mines in Bolivia.

ABC’s head office is in Lima, Peru, and it outsources all processes related to Production, Maintenance, Procurement and Human Resources to local Bolivian companies. ABC personnel manage in Bolivia only the Planning function.

Your plan starts in Lima, then you decide to go to Bolivia and fly back to Lima to audit the Quality Function and Top Management and conduct the closing meeting.

What would be your best decision when planning the audit in Bolivia?

A.

Proceed with the audit in Bolivia, including only ABC personnel of the Planning function.

B.

Proceed with the audit in Bolivia, including only ABC personnel and review, when you are back in Lima, the results of ABC’s internal audits to evaluate the performance of the outsourced processes.

C.

Proceed with the audit in Bolivia, including all ABC personnel and all outsourced processes.

D.

Tell the Certification Body you work for that ABC cannot outsource all Production, Maintenance, Procurement and Human Resources processes in Bolivia.