Which of the following conflict resolution styles involves a strict timeline and is commonly used within the construction industry?

A.

conciliation

B.

adjudication

C.

arbitration

D.

litigation

Which of the following will you put into box 1?

A.

subcontracting

B.

reputational damage

C.

penalty clause

D.

consequential loss

What is the purpose of a limitation on liability clause?

A.

it provides an accurate pre-estimate of potential loss

B.

it caps a company's exposure to risk

C.

it allows a party to claim on insurance if something goes wrong

D.

it passes the responsibility to the other party

Which of these statements about Guarantees are TRUE? Select 2

A.

A Guarantee is a secondary obligation of a contract

B.

A guarantor's responsibility is higher than the Principle

C.

A guarantee is a promise to repair or replace an item within a defined period of time

D.

A guarantor's responsibility cannot be higher than the Principle

Robert has a contract with Farmer Ted who provides his manufacturing firm with potatoes. There is a contract in place, signed by both parties that Ted will deliver 2 tonnes of potatoes per week. Due to changes in demand, Robert would like Ted to start providing 3 tonnes of potatoes every three weeks. What must be in place for this change to occur?

A.

a variation clause and a new liquidated damage fee

B.

a variation clause and a signed agreement by both parties

C.

a notification of change and adequate compensation

D.

a notification of change and indemnity

Which of the following will you put into box 3?

A.

anticipatory breach

B.

fundamental breach

C.

payment terms

D.

specification

Fishfingers Ltd has a contract with a supplier of cod. When the contract was set up it was not known how important specific delivery times would be for the arrival of the fish. After several months it has now become apparent that delivering the fish within 3 hours of them being caught is fundamental to the contract as delayed delivery results in poorer quality Fish Fingers. When the contract was set up what was the delivery times?

A.

a condition of the contract

B.

a warranty

C.

an innominate term

D.

a time is of the essence clause

Which of the following will you put into box 5?

A.

liability

B.

payment terms

C.

liquidated damages

D.

Contract variation

Which of the following is a source of breach in a contract?

A.

negligence

B.

liability

C.

force majeure

D.

warranty

What is a Prime Contract?

A.

A contract between a buyer and main supplier

B.

A contract between an end customer and a company which has full responsibility for its performance

C.

A contract between a supplier and a subcontractor

D.

A contract between a public sector organisation and the taxpayer