Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

PMI PMI-001 - Project Management Professional v5

Page: 11 / 14
Total 918 questions

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

A.

Customers.

B.

Business partners.

C.

Sellers.

D.

Functional managers.

The links between the processes in the Process Groups are often:

A.

Intuitive

B.

Iterative

C.

Measured

D.

Monitored

Information collected on the status of project activities being performed to accomplish the project work is known as what?

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

When is a project finished?

A.

After verbal acceptance of the customer or sponsor

B.

After lessons learned have been documented in contract closure

C.

When the project objectives have been met

D.

After resources have been released

During which process would you obtain stakeholders’ formal acceptance of the completed project scope?

A.

Quality control

B.

Scope verification

C.

Scope control

D.

Close project

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

A.

Monitor and Control Project Work

B.

Perform Quality Assurance

C.

Close Project or Phase

D.

Control Scope

Procurement audits, negotiated settlements, and a records management system are tools and techniques used in which Procurement Management process?

A.

Close Procurements

B.

Administer Procurements

C.

Plan Procurements

D.

Conduct Procurements

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Which is the correct formula for calculating expected activity cost for three-point estimating?

A.

Ce = (C0 + 6Cm + Cp)/4

B.

Ce = (6C0 + Cm + Cp)/4

C.

Ce = (C0 + 4Cm + Cp)/6

D.

Ce = (C0 + C„, + 4Cp) / 6

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:

A.

training, testing, and warranty work.

B.

equipment, rework, and scrap.

C.

training, document processes, and inspections.

D.

inspections, rework, and warranty work.

An output of the Direct and Manage Project Work process is:

A.

Deliverables.

B.

Activity lists.

C.

A work breakdown structure.

D.

A scope statement.

The procurement process that documents agreements and related documentation for future reference is known as:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Which of the following is a complete set of indexed contract documentation, including the closed contract?

A.

Procurement package

B.

Negotiated settlements

C.

Procurement file

D.

Procurement management plan

Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?

A.

Portfolio

B.

Process

C.

Project

D.

Program

Which of the following characteristics are found in a functional organizational structure?

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager's role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

The process of identifying and documenting relationships among the project activities is known as:

A.

Control Schedule.

B.

Sequence Activities.

C.

Define Activities.

D.

Develop Schedule.

When closing a project or phase, part of the process may require the use of which type of analysis?

A.

Reserve analysis

B.

Regression analysis

C.

Document analysis

D.

Product analysis

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

A.

Interactive communication

B.

Claims administration

C.

Conflict management

D.

Performance reporting

Which organizational process assets update is performed during the Close Procurements process?

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests