You are project manager and working on gathering requirements and estimating for the project. Which process group are you in?

A.

Planning

B.

Monitoring and Controlling

C.

Executing

D.

Initiating

Reverse analysis is a tool or technique in all of the following processes EXCEPT:

A.

Monitor and Control Risks

B.

Activity resource estimation

C.

Cost estimation

D.

Determine Budget

Bar charts generally illustrate:

A.

Progress of status.

B.

The critical path.

C.

Budget relation ships.

D.

Logical relationships.

You have been assigned to take over a project that is 60 percent complete according to the schedule. After evaluation, you find that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action you will take?

A.

Add new resource to the project and complete the project on schedule.

B.

Show your evaluation to sponsor.

C.

Ask your senior manager to deal with this.

D.

Turn the project back to the previous project manager.

The responsibility assignment matrix is a project management tool used to ________.

A.

Ensure team members understand their specific roles.

B.

Develop the work breakdown structure based on available resources.

C.

Establish project members availability to work on the project.

D.

Depict the project's organizational structure.

Ishikawa diagrams are used in which of the following processes?

A.

Perform quality control

B.

Create WBS

C.

Develop Schedule

D.

Plan Risk Management

You are a project manager with several years of experience in project management. You have just accepted your first project in a foreign country. You have been in the country a week or two and are experiencing some disorientation. This is known as which of the following?

A.

Collocation

B.

Diversity shock

C.

Global culturing

D.

Culture shock

What is the BEST way to accomplish resource planning?

A.

Identify required resources and allocate them to all project activities.

B.

Identify required resources in the project charter.

C.

Identify available resources and allocate them to all activities in the current phase of the project.

D.

Identify the resources that performed past similar projects, and allocate them to all project activities.

Monte Carlo analysis is a form of what type of analysis?

A.

Critical path method

B.

Schedule compression

C.

What if scenario analysis

D.

Resource leveling

Fast tracking involves:

A.

Developing workarounds for previous problems.

B.

An increase in project risk.

C.

Getting people to work longer with overtime.

D.

Meeting schedule objectives by adding resources.

A project schedule can be presented in various formats. All of the following are valid formats of the project schedule EXCEPT:

A.

Activity-on-node diagram

B.

Logic bar chart

C.

Time-scaled schedule network diagram

D.

Flow charts

You have been assigned to a project where the objective is to create a new building. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure you are working for?

A.

Projectized organization

B.

Weak matrix organization

C.

Balanced matrix organization

D.

Functional organization

Based on the PMBOK, who is ultimately responsible for the project quality?

A.

Project team

B.

Project manager

C.

QA manager

D.

Validation engineer

Your project sponsor has asked you to produce a Risk Management Plan for your current project. Which of the following best describes the plan you should adopt for your project?

A.

The plan must include the predefined risk management policies as they relate to the organization

B.

The plan must ensure that the level of details and risk management efforts are commensurate with the level of risk and importance of the project

C.

The plan must be predefined templates as defined by the organization

D.

The plan must include the predefined roles and responsibilities as they relate to risk management.

The peak point of Maslow's hierarchy is called:

A.

Survival.

B.

Safety.

C.

Physiological satisfaction.

D.

Self-actualization.