AOA refers to _____________.

A.

Arrow Diagramming Method [ADM]

B.

Precedence Diagramming Method [PDM]

C.

Fragment Network

D.

None

According to the PMBOK Guide, the project statement of work (SOW) should contain or reference all the following elements except?

A.

Business need, strategic plan, and product scope description

B.

Requirements, business need, and stakeholder expectations

C.

Strategic plan, product scope description, stakeholder influences, and business need

D.

Project purpose, business case, stakeholder influences, and product scope description

Analogous estimating ____________.

A.

Uses bottom-up estimating techniques

B.

Uses the actual costs from a previous, similar project

C.

Is synonymous with top-down estimating

D.

Both B and c are correct

___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.

A.

Procurement Management

B.

Planning Management

C.

Scope Management

D.

Control Management

Which of the following statements concerning compromise as a conflict resolution is false?

A.

Neither party wins but both parties get some degree of satisfaction.

B.

Important aspects of the project may be hindered in order to achieve personal objectives.

C.

Compromise is generally considered a lose-lose situation.

D.

A definitive resolution is seldom achieved.

Life cycle costing __________________.

A.

Includes acquisition, operating, and disposal costs when evaluating various alternatives

B.

Includes only the cost of the development or acquisition of a product or service

C.

Does not take into consideration the effect of project decisions on the cost of using the resulting product

D.

Botn B and c are correct

Cost of quality includes ___________.

A.

Cost of all work to build a product or service that conforms to the requirements

B.

Training programs

C.

Cost of all work resulting from non-conformance to the requirements

D.

Al1 of the above

All of the following are outputs from Report Performance EXCEPT _________.

A.

Trend analysis

B.

"S" curves, histograms, bar charts, and tables

C.

Performance reports

D.

Change requests

A project is considered successful when _______________.

A.

The project meets or exceeds the expectations of the stakeholders

B.

The product of the project has been manufactured

C.

The project sponsor announces the completion of the project

D.

None of the above

Completion of a product scope is measured against which of the following:

A.

WBS and WBS Dictionary

B.

Product Requirements

C.

Project Management Plan

D.

Product Management Plan

80% of the problems are found in 20% of the work is a concept of _________.

A.

Edward Deming

B.

PhiliP Crosby

C.

Juran

D.

Pareto

The process of monitoring specific project results to determine if they comply with relevant quality standards is called _______________.

A.

Quality Assurance

B.

Quality Control

C.

plan Quality

D.

Quality Review

Which of the following Project Scope Management Process defines how scope will be verified?

A.

Control Scope

B.

Verify Scope

C.

Define Scope

D.

Collect Requirements

Which of the following is part of the expectancy theory of motivation?

A.

Clear, specific, and challenging goals generally motivate team members.

B.

Project managers should ensure that tasks assigned to project participants match their skills and the organizational climate is conducive to helping them meet their needs and achieving a sense of competence.

C.

People tend to be highly productive and motivated if they believe their efforts will lead to successful results and that success will lead to personal rewards.

D.

Both B and C are true.

Which of the following contract types places the greatest risk on the seller?

A.

Cost-plus-fixed-fee contract

B.

Cost plus-incentive-fee contract

C.

Fixed-price-incentive contract

D.

Firm-fixed-price contract