An input to the Collect Requirements process is the:

A.

stakeholder register.

B.

project management plan.

C.

project scope statement.

D.

requirements management plan.

Which characteristics do effective project managers possess?

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Plan-do-check-act is also known as:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Which risk response strategy is common for both positive and negative risks?

A.

Share

B.

Accept

C.

Mitigate

D.

Transfer

Funding limit reconciliation is a tool and technique used in which process?

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

The initial development of a Project Scope Management plan uses which technique?

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

A.

Communications management plan

B.

Human resource plan

C.

Quality management plan

D.

Procurement management plan

Which process requires implementation of approved changes?

A.

Direct and Manage Project Execution

B.

Monitor and Control Project Work

C.

Perform Integrated Change Control

D.

Close Project or Phase

The process to ensure that appropriate quality standards and operational definitions are used is:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Which of the following is a tool or technique used in the Acquire Project Team process?

A.

Networking

B.

Training

C.

Negotiation

D.

Issue log

A tool and technique used during the Define Scope process is:

A.

facilitated workshops.

B.

observations.

C.

questionnaires and surveys.

D.

group creativity techniques.

Which of the following is an input to Direct and Manage Project Execution?

A.

Performance reports

B.

Project charter

C.

Outputs from planning processes

D.

Enterprise environmental factors

Which of the following is a tool and technique used to monitor risk?

A.

Technical performance measurement

B.

Cost performance baseline

C.

Benchmarking

D.

Cost of quality

The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:

A.

dictionary.

B.

chart.

C.

report.

D.

register.

The process of identifying specific actions to be performed to produce project deliverables is:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.