Pre-Summer Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 4 / 9
Total 278 questions

A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.

How should the risk manager manage the risk level?

A.

Communicate risk levels only to the supportive stakeholders.

B.

Advise the sponsor to meet with the stakeholders to discuss the risk levels.

C.

Collaborate with the project manager to communicate risk levels to stakeholders.

D.

Coach the project manager on communicating risk levels to stakeholders.

At an oil and gas company, a major unified management information system is to be implemented. The project manager noted that risks gathered from the organization ' s business functions are not properly identified and categorized, making it difficult to develop an effective risk response.

How should the project manager handle this situation?

A.

Outsource conducting the risk response plan to risk consultants.

B.

Ask functional managers to improve their risk register and process.

C.

Adjust the risk response plans to effectively handle the identified risks.

D.

Coach the functional groups on how to properly conduct the process.

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

A.

Use the Delphi technique involving experts who have identified opportunities in the past

B.

Interview more stakeholders who have a positive mindset

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

After starting a new pipeline project, a risk manager schedules an initial meeting with the project sponsor. For the meeting, the project sponsor requests a presentation of the risks that have the most impact on achieving the project objectives.

What should the risk manager do to facilitate the sponsor ' s ask?

A.

Monte Carlo analysis

B.

Qualitative risk analysis

C.

Sensitivity analysis

D.

Quantitative risk analysis

A risk manager is assigned to a new system deployment project with a strict contractually agreed-on schedule. One of the key risks identified is the availability of experts because many are shared on other strategic projects in the organization.

What should the risk manager do to address this situation?

A.

Implement a disciplined tracking method and report to stakeholders accordingly.

B.

Call for a project team meeting to review risk strategies and make required adjustments.

C.

Escalate the staffing topic to the sponsor and request more budget for contingencies.

D.

Revisit the project charter for scope adjustments and sign them off with the customer.

During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be

mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.

Which action should the risk manager take to address this risk?

A.

Accept the identified risk because other stakeholders feel that there are higher priority risks to address.

B.

Mitigate the identified risk in order to reduce the probability of impacting the stakeholder ' s team.

C.

Escalate the identified risk to the project sponsor and allow them to determine the best course of action.

D.

Add the identified risk to the risk register for future probability and impact analysis.

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks ' severity, and update the risk register.

A risk manager monitors risks on a medium-sized project by collecting inputs and data from individual project team members. What output is produced by the risk manager after analyzing the information they receive?

A.

Updated probability and impact matrix

B.

Updated risk register

C.

Updated mitigation plans

D.

Updated project scheduleÂ