Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam

Page: 6 / 8
Total 264 questions

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

A company manages confidential customer information, and a data breach exposing sensitive information was discovered. What should the risk manager do?

A.

Execute the security risks contingency plan.

B.

Get a report of customers affected by the risk.

C.

Identify residual and secondary risks.

D.

Coordinate a response with the risk owner.

A product roadmap should contain which of these primary components?

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?

A.

Include all stakeholders in the project's governance.

B.

Communicate response strategies to all stakeholders.

C.

Ignore any risks beyond stakeholders' tolerance.

D.

Consider stakeholders' positions and opinions regarding the project’s output.

There is confusion among risk action owners on a project about when and under which conditions they should initiate risk responses. Project team members often need to consult with the risk manager to get this conflict resolved.

What should the risk manager do to resolve this recurring situation?

A.

Review the stakeholders' risk appetite.

B.

Revisit the risk thresholds and triggers.

C.

Update the risk response strategies.

D.

Provide coaching to the risk action owners. 

Which statement describes the risk portrayed on the risk matrix heat map below?

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

An external vendor needs to be contracted to provide additional capacity and expertise to a project team to reduce the probability of delays in a project. The contracts department is raising a concern about confidentiality risks not addressed in the proposed contract and missing from the risk register.

What should the risk manager do next?

A.

Assess the identified secondary risk.

B.

Implement the risk response plan.

C.

Implement the risk contingency plan.

D.

Communicate the identified residual risk.