PMI PMI-RMP - PMI Risk Management Professional (PMI-RMP) Exam
After completing the risk register, many team members feel there is a lack of time prioritization for one of the identified risks What are the team members referring to?
A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?
At the beginning of a small project, the risk manager facilitates workshops to identify and analyze risks. At the end of the sessions, a stakeholder says that there should be no need to meet again about the risk register now that it ' s complete since it is such a short and simple project.
How should the risk manager respond to this comment?
A company has implemented a policy requirement for employees to use complex passwords and update them regularly. A few employees are unable to make the changes, which increases the likelihood of cybercriminals compromising their passwords.
What should the risk manager do?
During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.
What should the risk manager do to resolve the sponsor and project team members ' concerns about risk identification?
An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.
What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)
During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.
What action should the project manager take?
When should the benefits of quantitative risk analysis be weighed against the effort required to ensure that the additional insights and value justify the extra effort?
During the construction of a housing development, a project team realizes they exceeded their materials budget during the first of three execution stages. The risk manager observed that the team did not notice that the cost of the materials increased due to continuous inflation in the steel market.
What could have been done during project planning to avoid overspending?
A software development project team was preparing for a phased release when an unknown and unexpected risk occurred with potential for delaying one of the features for the planned release. The project team decided to go ahead with the release and address this missing feature at a later date. One of the end users learned about this and strongly opposed the planned release.
What should the risk manager have done to prevent this situation?
