Summer Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ecus65

Scrum PSM-I - Professional Scrum Master I

Page: 2 / 8
Total 268 questions

A Scrum Team is experiencing a growing list of impediments. Which techniques would be most

helpful in this situation?

(choose the best two answers)

A.

As a Scrum Team, prioritize the list and work on them in order.

B.

The Scrum Master discusses the impediments with the Scrum Team.

C.

The Product Owner should add the open impediments to the Product Backlog.

D.

Arrange a triage meeting with management.

The length of a Sprint should be:

A.

Short enough to keep the business risk acceptable to the Product Owner.

B.

Short enough to be able to synchronize the development work with other business events.

C.

No more than one calendar month.

D.

All of these answers are correct.

The Daily Scrum is an event that happens every day. What would be three key concerns if the frequency were to be lowered to every two or three days? (Choose three.)

A.

Opportunities to insect and adapt the Sprint Backlog are lost.

B.

Impediments are raised and resolved more slowly.

C.

The Product Owner cannot accurately report progress to the stakeholders.

D.

Too much work is spent updating the Scrum board before the meeting.

E.

The Scrum Master loses the ability to update the Gantt chart properly.

F.

The Sprint plan may become inaccurate.

What is the time-box for the Sprint Planning meeting?

A.

4 Hours for a monthly Sprint.

B.

8 Hours for a monthly Sprint.

C.

Monthly.

D.

Whenever it is done.

When is a Sprint over?

A.

When the Product Owner says it is done.

B.

When all Product Backlog items meet their definition of “Done”.

C.

When all the tasks are completed.

D.

When the time-box expires.

Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.

Run the Daily Scrum.

B.

Prioritize the Development Team’s work on the Sprint Backlog.

C.

Update the Sprint burndown chart.

D.

Answer questions from the Development Team about items in the current Sprint.

E.

Work with the stakeholders.

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

A Development Team is required to deliver a done Increment by the end of a Sprint. Select two statements that explain what “Done” means. (Choose two.)

A.

All work the Development Team is willing to do.

B.

Ready for integration.

C.

No work left from the definition of “Done”.

D.

Whatever the Product Owner defines as quality.

E.

All work to create software that is ready to be released to end users.

Who should make sure everyone on the Development Team does their tasks for the Sprint?

A.

The Project Manager.

B.

The Product Owner.

C.

The Scrum Master.

D.

The Development Team.

E.

All of the above.

True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.

A.

True

B.

False