An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Which Scrum Value is affected by a lack of trust in the Scrum Team?

A.

Focus

B.

Respect

C.

Openness

D.

Courage

E.

Commitment.

F.

All of the above

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

A.

True

B.

False

True or False: The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal.

A.

True

B.

False

What two factors are best considered when establishing the Sprint length? (Choose two.)

A.

The organization has mandated similar length sprints.

B.

The level of uncertainty over the technology to be used.

C.

The frequency at which team formation can be changed.

D.

The risk of being disconnected from the stakeholders.

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Which two things should the Development Team do during the first Sprint? (Choose two.)

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

A.

Ensuring that the most valuable functionality is produced first, at all times.

B.

Interacting with stakeholders.

C.

Providing the Development Team with detailed specifications.

D.

Describing features as Use Cases.

E.

Creating detailed functional test cases.

What are two responsibilities of testers in a Development Team? (Choose two.)

A.

Verifying the work of programmers.

B.

Everyone in the Development Team is responsible for quality.

C.

Tracking quality metrics.

D.

Finding bugs.

E.

Scrum has no “tester” role.

The Product Backlog is ordered by:

A.

The Product Owner with the most valuable items placed at the top.

B.

Risk, where safer items are at the top, and riskier items are at the bottom.

C.

Items are randomly arranged.

D.

Size, where small items ale at the top and large items are at the bottom.