As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

A.

Inform the Product Owner at the Sprint Review, but prior to the demonstration.

B.

Find another Scrum Team to give the excess work to.

C.

As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.

D.

Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

A.

Economic Value Added.

B.

Respect.

C.

Focus.

D.

Earned Value.

E.

Courage.

What is the role of management in Scrum?

A.

To facilitate the Scrum Teams with insights and resources that help them improve.

B.

To monitor the Development Team’s productivity.

C.

To identify and remove people that aren’t working hard enough.

D.

To continually monitor staffing levels of the Development Team.

A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give? (Choose the best answer.)

A.

Product Backlog items must be estimated in story points.

B.

Estimates are made by the people doing the work.

C.

Estimates must be in relative units.

D.

Scrum forbids estimating.

E.

Estimates are made by the Product Owner, but are best checked with the Development Team.

The Development Team should have all the skills needed to:

A.

Turn Product Backlog items into an Increment of potentially releasable product functionality.

B.

Do all of the development work, except for specialized testing that requires additional tools and environments.

C.

Complete the project within the date and cost as calculated by the Product Owner.

Why is the Daily Scrum held at the same time and same place?

A.

The consistency reduces complexity.

B.

The place can be named.

C.

The Product Owner demands it.

D.

Rooms are hard to book and this lets it be booked in advance.

Which statement best describes the Sprint Review?

A.

It is used to congratulate the Development Team if it did what it forecast, or to punish the Development Team if it failed to meet its forecast.

B.

It is a demo at the end of the Sprint for everyone in the organization to check on the work done.

C.

It is a mechanism to control the Development Team’s activities during a Sprint.

D.

It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what to do next.

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

A.

When the Product Owner identifies new work.

B.

As soon as possible after they are identified.

C.

When the Scrum Master has time to enter them.

D.

During the Daily Scrum after the Development Team approves them.

Which are appropriate topics for discussion in a Sprint Retrospective? (Choose the best three answers.)

A.

Arranging the Sprint Backlog for the next Sprint.

B.

The value of work currently represented in the Product Backlog.

C.

Team relations

D.

Definition of Done.

E.

How the Scrum Team does its work.

When multiple Scrum Teams are working on the same product, should all of their Increments be

integrated every Sprint? (choose the best answer)

A.

Yes, but only for Scrum Teams whose work has dependencies.

B.

No, that is tar too nard and must be done in a hardening Sprint

C.

No, each Scrum Team stands alone.

D.

Yes, in order to accurately inspect what is done.