What is the first task of product-based planning?

A.

Produce the Initiation Stage Plan

B.

Write the Project Product Description

C.

Identify dependencies

D.

Create the product breakdown structure

Which is a typical core activity within configuration management?

A.

Quality assurance

B.

Risk management

C.

Verification and audit

D.

Progress reporting

Which is NOT one of the PRINCE2 integrated elements?

A.

Tailoring PRINCE2 to the project environment

B.

The processes

C.

The products

D.

The themes

Which is a benefit of using PRINCE2?

A.

Enables the management of projects as well as of 'business as usual' activities

B.

Can be tailored by leaving out elements of the method for some projects

C.

Can be applied to any type of project

D.

Avoids the need to involve corporate or programme management

Which is a true statement about acceptance criteria?

A.

Acceptance criteria are used to produce the customer's quality expectations

B.

Acceptance criteria are less specific and precise than customer's quality expectations

C.

Once agreed, acceptance criteria CANNOT be changed

D.

Acceptance criteria should be agreed between the customer and the supplier

Which does NOT reflect the PRINCE2 principle of continued business justification?

A.

There must be a justifiable reason for starting a project

B.

The business justification drives decision making

C.

If a project is no longer forecast to deliver a financial benefit, it should be stopped.

D.

If a project can no longer be justified, it should be stopped

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

A.

Specify the desired result

B.

Provide the resources and skills to deliver the desired result

C.

Pay for the project

D.

Specify the benefits of the project

Identify the missing word(s) in the following sentence. PRINCE2 recommends three levels of [ ? ] to reflect the needs of the different levels of management involved in a project.

A.

Management strategies

B.

Plan

C.

Stakeholder interests

D.

Time-driven controls

Which is a purpose of an End Project Report?

A.

Identify individuals or groups that need to be told that the project is coming to an end

B.

Review how well the project performed against the Project Initiation Documentation used to authorize it

C.

Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed

D.

Ensure that key project information is archived and made secure

Which role is responsible for creating Checkpoint Reports?

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support