A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.

What should the program manager do next?

A.

Ask the finance department to increase the program budget

B.

Escalate the issue to the program governance board

C.

Ask key stakeholders to influence the program sponsor

D.

Direct component project managers to archive all relevant project documents

External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor

What should the program manager do?

A.

Add the vendor to the approved list

B.

Report an ethics violation

C.

Agree to engage the vendor due to the program governance board member's program influence

D.

Initiate a new vendor selection bid process

After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.

What should the program manager do next?

A.

Accelerate the projects and components of the program that replace the two legacy systems

B.

Analyze the impact of accelerating the program, and present the pros and cons to the program sponsor

C.

Identify the parts of the program that need to be accelerated and. if it is cost effective and increases benefits realization, implement the change

D.

Create several "what-if" scenarios of alternatives to present to the program sponsor

A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.

What should the program manager do to ensure the success of the program?

A.

Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered

B.

Host a kick-off meeting, request preliminary requirements from the marketing department, conduct a design session present the steering committee with a solution that meets the requirements: and meet with interested vendors

C.

Ask a senior marketing executive to act as the program sponsor and participate on the steering committee: require steering committee representation from the IT legal, and other key departments, validate that the chosen solution meets the requirements

D.

Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gam the confidence of the legal department

Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.

What should program A's program manager update and review first with the stakeholders?

A.

Benefits sustainment plan

B.

Benefits register

C.

Benefits management plan

D.

Benefits transition plan

An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.

How should the junior project manager respond to this request?

A.

Accept the assignment, identify the skill gaps and request training

B.

Reject the assignment, because of the ethical requirement not to accept work for which the project manager is not qualified

C.

Accept the assignment as a challenge and an opportunity to acquire new skills and seek advice from a senior project manager

D.

Reject the assignment because of fear of failure and resulting negative career impact

In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?

A.

CD

B.

SD

C.

PD

D.

DD

What would prevent a program manager from completing program closure once a program has been completed?

A.

Failure to update the financial management plan

B.

Failure to update the benefits register

C.

Incomplete realization of all program benefits

D.

Failure to obtain program steering committee approval

For a backbone distribution system serving a usable floor space of ≈ 8,920 m2 (96,000 ft2), the MINIMUM slot area to be used for this back bone is

A.

≈ 0.040 m2 (60 in2)

B.

≈ 0.048 m2 (72 in2)

C.

≈ 0.056 m2 (84 in2)

D.

≈ 0.064 m2 (96 in2)

A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.

At this stage of the program, what is the first step?

A.

Develop a program work breakdown structure

B.

Identify and quantify business benefits of the program

C.

Determine and prioritize the various components of the program

D.

Prepare a program organization chart covering both sales and production