A multiyear program is ready to conclude. It has achieved all business objectives and is delivering its intended benefits. However the program sponsor is not willing to sign the formal program closure acceptance document and the program continues to incur operational costs.
What should the program manager do next?
External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor
What should the program manager do?
After meeting with the program sponsor and stakeholders, the program manager is asked by the sponsor to accelerate the program to replace two legacy financial systems. The legacy systems are at risk of premature failure.
What should the program manager do next?
A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?
An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization.
How should the junior project manager respond to this request?
In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?
What would prevent a program manager from completing program closure once a program has been completed?
For a backbone distribution system serving a usable floor space of ≈ 8,920 m2 (96,000 ft2), the MINIMUM slot area to be used for this back bone is
A company initiates a program to reorganize its sales and production departments. Three production departments are located at the three production plants next to the company's headquarters Five regional sales departments are located at different locations around the world.
At this stage of the program, what is the first step?