What is one approach to unlock the intrinsic motivation of knowledge workers?

A.

Centralize decision-making

B.

Provide autonomy

C.

Reduce work in process (WIP) limits

D.

Strive to achieve a state of continuous flow

What is the purpose of Customer Centricity?

A.

To design custom-built Customer Solutions

B.

To interpret market rhythms

C.

To build small, partial systems just in time

D.

To understand the Customer's needs

Which statement is true about pair work in the Scaled Agile Framework?

A.

It comes from pair programming in Extreme Programming (XP)

B.

It is a best practice that team members should spend 50% to 100% of the time in pair work

C.

It occurs during Iteration Planning

D.

It is for developers only

A cumulative flow diagram focuses on which curves?

A.

Arrival curve ("to do") and evolution curve ("change")

B.

Implementation curve ("movement") and departure curve ("done")

C.

Backlog curve ("work") and departure curve ("done")

D.

Arrival curve ("to-do") and departure curve ("done")

Which is an aspect of systems thinking?

A.

Mastery drives intrinsic motivation

B.

Optimizing a component does not optimize the system

C.

The length of the queue impacts the wait time

D.

Cadence makes routine everything that can be routine

Which statement correctly describes one aspect of the team's commitment at the end of PI Planning?

A.

A team commits to all the Features they put on the ART planning board

B.

A team commits only to the PI Objectives with the highest business value

C.

A team commits to all the Stories they put on their PI plan

D.

A team does not commit to uncommitted objectives

What is one benefit of Design Thinking?

A.

The Solution is accountable

B.

The Solution is actionable

C.

The Solution is sustainable

D.

The Solution is reliable

What must management do for a successful Agile transformation?

A.

Commit to quality and take responsibility to change the system

B.

Send someone to represent management, and then delegate tasks to these individuals

C.

Establish direct lines of report to the RTEs

D.

Identify and area of the transformation they can control

What brings structure to analysis and decision making around Epics?

A.

Portfolio Vision

B.

Portfolio Backlog

C.

Portfolio Canvas

D.

Portfolio Kanban

During the final plan review, ART PI risks are ROAM'ed. What do the letters in ROAM represent?

A.

Resolved, Owned, Approved, Mitigated

B.

Resolved, Owned, Accepted, Mitigated

C.

Resolved, Owned, Assigned, Mitigated

D.

Resolved, Owned, Active, Mitigated