Materials that are easily reduced to a granular or powdery condition after placement are known as:

A.

friable materials.

B.

calcined frits.

C.

mineral additives.

D.

granular grog.

Ceramic fiber batten strips shall be:

A.

the same grade as hot face material.

B.

anchored with Lock Studs.

C.

anchored with staples.

D.

a maximum length 3 ft (0.9 m).

The quantity of manufactured refractory that has the same formulation as that prepared in an uninterrupted manufacturing operation is called a:

A.

pallet

B.

test sample

C.

production run

D.

bag

Maximum allowable crack length, visible on the surface of a dense firebrick, is:

A.

1/4 in. (6 mm)

B.

3/8 in. (10 mm)

C.

1/2 in.(12 mm)

D.

3/4 in. (19 mm)

For as-installed testing in casting applications, what is the minimum number of cast samples required by each mixing crew per material per shift?

A.

One

B.

Two

C.

Three

D.

Four

For the qualification of the applicator/installer, they shall demonstrate their ability to install the refractory:

A.

to meet the specified quality standards utilized for the installation of work.

B.

by using the technique prescribed by the manufacturer no matter which material is used.

C.

free of visible voids, laminations on the hot face or working surface only for gunned lining.

D.

free of visible voids, laminations on the hot face or working surface only of the refractory lining.

The contractor on a field vibration casting job is preparing for a continuous pour that will last for three 12-hour shifts. The weather report predicts a nighttime low temperature of 35°F (2°C). How should the contractor be prepared?

A.

Have the castable dry mix heated to >50°F (10°C)

B.

Be ready to stop pouring if the temperature drops below 35°F (2°C)

C.

Make no special preparations

D.

Keep the install material and shell >50°F (10°C)

Conflicts in documents and/or drawings shall be resolved by the:

A.

inspector.

B.

owner.

C.

engineering company.

D.

inspector with 30 years of service/experience.

What is the size of a test specimen for permanent linear change of refractories?

A.

2 in. (50 mm) x 2-1/2 in. (64 mm) x 9 in. (230 mm)

B.

2-1/2 in. (64 mm) x 2-1/2 in. (64 mm) x 2 in. (50 mm)

C.

2 in. (50 mm) x 2 in. (50 mm) x 4 in.(100 mm)

D.

2 in. (50 mm) x 2 in. (50 mm) x 9 in. (230 mm)

Refractory samples cast during the mock-up are cured for a minimum of:

A.

8 hours.

B.

12 hours.

C.

18 hours.

D.

24 hours.