API API-936 - API 936 - Refractory Personnel

Page: 3 / 3
Total 85 questions

Which party provides the quality requirements for hammer testing, extent of cracking, and surface voids?

A.

The owner

B.

The contractor

C.

The refractory manufacturer

D.

The inspector

Newly applied cast linings must cure before stripping the forms per the:

A.

manufacturer's recommendations.

B.

owner's recommendations.

C.

MSDS.

D.

inspector's recommendations.

Test results received from cast sample mock-ups will serve to qualify the:

If application of hydraulic bonded or chemical setting refractory is interrupted, the refractory lining shall be:

A.

cut back within 1 hour.

B.

cut back within 30 minutes.

C.

immediately cut back to the shell between anchors.

D.

cut back to the shell in a straight line.

Who is responsible to approve refractory dryout procedures that have more than one heat source?

A.

Contractor

B.

Owner

C.

Manufacturer

D.

Inspector