The combination of which two structures creates the responsibility assignment matrix (RAM)?

A.

OBS and CBS.

B.

OBS and WBS.

C.

PBS and CBS.

D.

WBS and CBS.

The project manager's prime responsibility is to:

A.

deliver the benefits.

B.

define the requirements.

C.

sign off the business case.

D.

implement the project plan

Which of the following statements about estimating is true?

A.

Post project reviews are a prime source of estimating data.

B.

An estimated cost for a project must be 10 per cent to be any use

C.

If you cannot estimate task durations to within 20 per cent there is no point in developing a schedule.

D.

The project manager should always add 10 cent to peoples duration estimates to allow for natural optimism

Product breakdown structures illustrate the required scope of work by a hierarchical structure itemising the:

A.

components of each product.

B.

budget of each product.

C.

benefits of each product.

D.

risks of each product.

One of the main purposes of dividing a project into life cycle phases is to:

A.

break the work into controllable blocks in terms of effort and size.

B.

ensure the processes are properly maintained.

C.

ensure that the workforce is certain of their individual roles.

D.

provide a means Of producing overall project cost estimates.

What is defined as "the ability to influence and align others towards a common purpose"?

A.

Teamwork.

B.

Motivation.

C.

Management.

D.

Leadership

Configuration management can be used to control documents, information and:

A.

users.

B.

audits.

C.

stakeholders.

D.

assets.

Which of the following would be considered as a valid objective for the post project review?

A.

Plan the next project for the project team.

B.

Make proposals for the operation of the project deliverables.

C.

Improve future estimating accuracy.

D.

Plan how to complete the objectives of the project.

Which of these is a correct definition of an Estimate?

A.

The use of a range of tools and techniques to produce forecasts of the probable time or cost of completing work

B.

An educated guess that improves over time

C.

A forecast of the probable time or cost of completing work

D.

An estimate is an approximation of project time and cost targets that forms the basis of the contract

A communication management plan identifies the relevant information that should be communicated to:

A.

the project team.

B.

the project stakeholders.

C.

the project board.

D.

the project sponsor