The process that evaluates overall project performance to provide confidence is called:

A.

quality assurance.

B.

quality planning.

C.

quality control.

D.

quality audit.

Which one of the following takes place during closeout?

A.

Benefits realisation review.

B.

Final project review.

C.

Deliverables accepted by sponsor.

D.

Handover of relevant documentation

When no other changes are being considered to the project, this is usually termed as a:

A.

scope verification.

B.

change freeze.

C.

consolidated baseline.

D.

configuration control.

One purpose of a typical project business case is to:

A.

carry out earned value analysis.

B.

allocate resources to the project.

C.

analyse cost-benefit of the project.

D.

plan project work packages

When the project progresses through the life cycle. which one of the following aspects would be expected to occur?

A.

The accuracy of the estimate reduces and the level of contingency requirement increases.

B.

The accuracy of the estimate increases and the level of contingency requirement reduces.

C.

The accuracy and level Of contingency requirement both increase.

D.

The accuracy and level of contingency requirement both reduce.

Which stakeholders are likely to form the main part of a project governance board?

A.

Project sponsor, project manager and quality manager.

B.

Corporate management, project sponsor, quality manager and project office.

C.

Sponsor, supplier representative and user representative.

D Sponsor, project manager and senior project team members.

What is the likely decision to arise from the response stage of the risk management process?

A.

Whether to proceed with the project or recommend termination.

B.

Whether the process being used is robust enough for the project being undertaken.

C.

Whether to proactively invest to bring the exposure to risk within tolerable levels.

D.

Whether to use brainstorming or a workshop to decide on the best response.

Which of the following is not a key element of project scope management?

A.

Define outputs.

B.

Identify outputs.

C.

Share outputs.

D.

Control outputs

Which of the following is an activity in a typical configuration management process?

A.

Evaluation.

B.

Identification.

C.

Registration.

D.

Justification.

The purpose of a decision gate is to decide whether:

A.

the response to a risk is valid.

B.

a project is viable in line with the business case.

C.

the project delivered against the success criteria.

D.

lessons were effectively learned during the project.