Which of the following is a difference between deployment baselines in linear life cycles anditerative life cycles?

A.

Linear project life cycles set the deployment baseline for the whole project.

B.

In an iterative project life cycle the scope and quality are fixed in the deployment baseline.

C.

Only deployment baselines in iterative life cycles have an integrated baseline review.

D.

Only deployment baselines in linear life cycles have an integrated baseline review

Which one of the following best defines a benefit?

A.

A. positive result of stakeholder management.

B.

The successful management of a project.

C.

An improvement resulting from project deliverables.

D.

The successful delivery of project reports and updates.

The project team comprises:

A.

all those responsible to the project manager who are working towards the project objectives.

B.

the members of staff who are allocated full time to the project.

C.

the members of staff who report to the project manager and who carry out work on the project.

D.

all project stakeholders.

Which of the following are typical estimating methods? 1) Analytical 2) Budgeting 3) Analogous 4) Parametric

A.

1, 2 and 4

B.

1, 2 and 3

C.

1, 3 and 4

D.

2, 3 and 4

Which of the following activities is not in an extended project life cycle?

A.

Deployment.

B.

Termination.

C.

Adoption.

D.

Transition.

Which of the following statements about scheduling is false?

A.

Defines the sequence of activities.

B.

Considers work calendars and time contingency.

C.

Provides a baseline for safety considerations.

D.

Quantifies the required resources.

Which one of the following is captured in the Work Breakdown Structure (WBS)?

A.

The life cycle phases.

B.

The logical order of tasks.

C.

The scope of the project.

D.

Project costs.

Which of the following define leadership?

1) Ability to establish vision and direction

2) Developing team skills that enhance project performance3) Empowering and inspiring people to achieve success

4) Ability to influence and align others towards a common purpose

A.

1, 2 & 4

B.

1, 2 & 3

C.

2, 3 & 4

D.

1, 3 & 4

Which of the following BEST describes a project issue?

A.

An uncertain event that may or may not occur

B.

An opportunity that occurs through change control

C.

A problem that the project manager has to deal with on a day-to-day basis

D.

A problem that needs to be escalated to the next level of management for resolution

Which of the following would be considered most important when carrying out A. detailed evaluation of a change?

A.

Impact of change on baseline, risks and business case.

B.

The number of extra people required to deliver the change.

C.

How the change will be reported when it is implemented into the project.

D.

The configuration requirements Of the change when implemented into the project,