Which plain defined by DSDM, has a planning horizon that includes the end of a project?

A.

Timebox

B.

Detailed

C.

Delivery

D.

High-Level

Which of the key principles, for building and maintaining engagement throughout change, is demonstrated when we are able to talk about anything, maintain the relationship, and reach a good outcome?

A.

Inclusivity.

B.

Connectivity.

C.

Transparency.

D.

Dialogue.

How does the Post-Project phase add value to a project?

A.

Define how the operation of the solution will be managed

B.

Iteratively explores the low- level detail of the requirements

C.

Checks how well the expected business benefits have been met

D.

Brigs a baseline of the Evolving Solution into operational use

How is Quality ensured during Evolutionary Development?

A.

By managing objectives in a fixed time period

B.

By continuous verification

C.

By understanding and managing priorities

D.

By facilitating session to enable a group to work to achieve an agreed goal

Which of the following statements about the Project Approach Questionnaire (PAQ) are true?

    Should be revisited at the end of Foundations.

    Should be revisited each time Foundations is revisited.

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 is true