APMG-International AgilePM-Practitioner - Agile Project Management (AgilePM) Practitioner Exam
Total 184 questions
Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.
Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column
2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.
Each selection from Column 2 can be used once, more than once or not at all.


Using the Project Scenario, answer the following question about the activities in the Agile project lifecycle.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Assertion:-
1. The rooms and facilities must be deployed into live use at the end of each Timebox.
BECAUSE
Reason:
Evolutionary Development and Deployment must be combined in a Timebox where the integration of several teams is required.
2. The tasks associated with each Solution Development Timebox should be included
in the Delivery Plan.
BECAUSE
Reason:
A typical Delivery Plan will provide a schedule of Timeboxes and any other high level activities for the imminent Project Increment.
3. The development approach should have been agreed during Foundations.
BECAUSE
Reason:
The Development Approach Definition must be created before Evolutionary
Development can commence.
4. The resources from Timber Tigers and Earth Excavations should have been engaged
before the start of Evolutionary Development.
BECAUSE
Reason:
Commitment to delivery is based on pre-agreed resource levels at the project level.
5. A final Deployment phase should be held after Timebox C has completed.
BECAUSE
Reason:
The Deployed Solution is assessed post-project to confirm whether the expected benefits have been
achieved.


Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional
wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?
During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what
needed to be done before these would be acceptable.
Is this an appropriate application of Agile Project Management for this project?
There are several tests planned throughout the project to ensure the solution is fit for purpose and to validate the business solution as
it evolves.
Column 1 is a list of tests. For each test in Column 1, select from Column 2 the testing concept that it represents. Each selection from Column 2
can be used once, more than once or not at all.
Column 1
1) In order to get an objective
view, the financial transaction
function is to be tested by
someone from Finance who
has had no involvement in its
development.
2) Before the developer works on
the printing function for the
policy documents, the Sales
Manager will review a prototype
of the online application form
for the new coffee shop
insurance product with the
solution tester.
3) Security test scripts have been
provided by the company ' s
bank. These scripts will be used
to test the link from the
company ' s website to the
banking system, which is to be
developed specifically to achieve these tests
4.
The addition of the new coffee
shop insurance product may
threaten the stability of the
existing website. As a primary
route to market this is
unacceptable. The website ' s
capacity to run additional pages
is to be verified before any
other tests are performed.
5.
The Must Have and Should
Have requirements are to be
tested before the Could Have
requirements.
Column 2
Collaborative Testing
Repeatable Testing
Independent Testing
Prioritised Testing
Test-Driven Development

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
Which 2 statements explain why the Timber Tigers ' Site Manager would be an appropriate Solution Developer?