APMG-International AgilePM-Practitioner - Agile Project Management (AgilePM) Practitioner Exam

Several of the web developers working on the project have no Agile

experience. When answering the questions in the Project Approach

Questionnaire (PAQ), the Project Manager could not agree with the statement

'all members of the project understand and accept the DSDM approach'.

What action should the Project Manager take?

A.

Replace the web developers with experienced Agile practitioners.

B.

Agree with the statement in the PAQ and keep a close watch on the web

developers throughout the project.

C.

Organize a training workshop to brief all project-level and Solution

Development Team roles in the Agile approach.

D.

Accept that the web developers are experts in their field and will be

adopting their own approach throughout the project.

Answer the following questions about actions to be taken by different

roles.

The Business Sponsor has decided that the new coffee shop insurance

product website pages will include the financial transaction functionality to

support the end-to-end sales process. The Business Sponsor views this as a

valuable sales tool, enabling customers to pay for insurance policies online. If

successful, this new financial transaction functionality is to be made available

across all other insurance products. This is a new Must Have requirement.

All parties are to be invited to a workshop to discuss the additional work

required to deliver the required solution including the new Must Have

requirement. The areas to be discussed include specialist skills required and

possible legal, financial and technical standards to be adhered to.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 actions should the Business Sponsor take to implement the new Must

Have requirement?

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Check the viability of the project, following the inclusion of the new Must

Have requirement.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

E.

Assess the impact of the new Must Have requirement on the original

Business Case.

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?

A.

Accustomed to bringing in contract staff for short periods of time.

B.

Closely manages the building team so that they consistently produce high-quality work.

C.

Is able to represent the team in all daily meetings.

D.

An experienced builder who is good at turning a brief into a practical design.

E.

Is empowered by Timber Tigers' management to make decisions on the building work.

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

A.

The Project Manager should extend the timescale of Timebox B and shorten Timebox C.

B.

The Solution Development Team should change a Must Have requirement into a Should Have in the Prioritised Requirements List.

C.

The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities.

D.

The Project Manager should move a Must Have requirement from Timebox B into Timebox C.

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?

A.

The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.

B.

Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed.

C.

During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.

D.

The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.

E.

The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Delivery Plan?

A.

The Project Manager should include any known constraints associated with planning permission.

B.

The Project Manager should NOT need to identify any risks this early in the project.

C.

The approach to the project should be based on the Project Approach Questionnaire responses.

D.

The Earth Excavations' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.

E.

The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.

Which 2 actions should the Workshop Facilitator take when preparing for the workshop?

A.

Ask the Software Developer to provide an estimate of how much storage space would be required to hold photos and videos.

B.

Invite the Marketing Director to create a summary of the content they believe the system should hold and why.

C.

Assign ownership of the workshop to the Software Developer.

D.

Ask the IT Operations Manager to prepare the agenda for the workshop.

E.

Research other hotel reservation systems to form an opinion on what the content should be.

How should the Project Manager encourage the contractors to turn up on time?

A.

Place a penalty clause on all contractors for late arrival.

B.

Appoint Team Leaders to each of the electrical and plumbing teams.

C.

Encourage open and honest communication to re-establish an environment of trust.

D.

Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.