Weekend Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

APMG-International AgilePM-Practitioner - Agile Project Management (AgilePM) Practitioner Exam

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying

controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

A.

Encourage the Marketing Director to attend the End of Timebox Review.

B.

Attend the next Daily Stand-up to raise an issue about the windows.

C.

Prepare a summary of progress against plan, for presentation at the review.

D.

Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.

B.

The Solution Development Team should commence understanding and delivering the new requirement.

C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.

D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the

responsibilities of the roles in the Agile team.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion

    The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.

BECAUSE

The Project-level roles are responsible for directing, managing and co-

ordinating the project.

    The Procurement Manager is an appropriate representative of the end user of the solution.

BECAUSE

The Business Ambassador should be empowered to make decisions within

the boundaries of their role, without referral to higher authorities outside

the Solution Development Team.

    The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.

BECAUSE

Extra Solution Developers can provide a supporting role for a Lead

Developer.

    The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.

BECAUSE

The Business Ambassador is responsible for ensuring that business needs

are properly analysed.

    The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.

BECAUSE

The Business Visionary is responsible for promoting the business vision to

all interested parties.

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

A.

Present own interpretation of what the system should include.

B.

Present the group with a predefined specification of what should be included.

C.

Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.

D.

Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.

E.

Prepare a report describing the outcome of the workshop.

A three-month timeframe has been specified to catch the seasonal sales window.

Which Agile principle MOST influences this course of action?

A.

Focus on the business need.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Develop iteratively.

Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion :

1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.

BECAUSE

The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.

2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off

BECAUSE

The aim of the Investigation step within each Timebox is to complete as much of

the development work as possible.

3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.

BECAUSE

Each Timebox should comprise an Evolutionary Development phase and

Deployment phase.

4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.

BECAUSE

A typical Timebox Plan should provide a schedule of high-level activities for the

imminent Project Increment.

5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.

Reason

BECAUSE

The Solution Development Team is responsible for planning the detail of all the

work of each Timebox.

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.

Is this an appropriate action related to acceptance criteria?

A.

Yes, because this will allow the Solution Development Team to focus on the quality of the Solution Development Timebox's deliverable as a whole, in order to keep focus on the business need.

B.

Yes, because it will be easier to set acceptance criteria for the Solution Development Timebox as a whole, rather than setting specific acceptance criteria for each individual requirement.

C.

No, because the acceptance criteria for the Solution Development Timebox are just the amalgamation of the individual requirements' acceptance criteria, with nothing extra.

D.

No, because the Solution Development Timebox objective will change if any new requirements emerge or any lower priority requirements are de-scoped.

Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not

happen again.

Which Agile principle MOST influences this course of action?

A.

Focus on the business need.

B.

Deliver on time.

C.

Build incrementally from firm foundations.

D.

Demonstrate control.

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions.

Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.

The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director's leadership team in the UniCo building. At the last Operations' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.

Is this an appropriate approach to reward the brain in the need for 'status', and

why?

A.

No, because 'status' should be rewarded by ensuring open, two-way

communication using rich channels.

B.

No, because the Application Manager's knowledge and skills are still

relevant and there no threat to 'status'.

C.

Yes, because highlighting cooperation provides an opportunity for the

Applications Manager to learn and develop.

D.

Yes, because praising people publicly helps to improve a person's

informal importance in the organization.

The Change Manager has read Goleman's articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that

leadership style can improve organizational culture and performance as measured by staff surveys.

Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the

organization.

Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each

recommendation in Column 1, select from Column 2 the 'dimension' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be

used once, more than once or not at all.