You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

A.

$-00,000

B.

$200,00

C.

$50,000

D.

None of the above

Project scope is _____________.

A.

The features and functions that are to be included in a product or service

B.

The work that must NOT be done in order to deliver a product with the specified features and functions

C.

Part °ftne project charter

D.

Part of sow

Administrative closure is the process that ________.

A.

Closes all activities pertaining to a specific project

B.

Collects user acceptance of the project product or service

C.

Includes all the activities needed to validate the project products and services

D.

Al1 of the above

___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.

A.

Procurement Management

B.

Planning Management

C.

Scope Management

D.

Control Management

In PMBOK, the seller is ________ to the project team.

A.

Internal

B.

External

C.

Outside

D.

Assigned

Which of the following subsidiary plan contains the quality objectives for the project?

A.

Quality baseline

B.

Quality management plan

C.

Process improvement plan

D.

QA checklist

Who has the responsibility for informing the final deliverable to all stakeholders?

A.

Project Manager

B.

Sponsor

C.

Team Lead

D.

Management

What is a corrective action?

A.

An action that brings future project events Into alignment with the project plan

B.

An action to correct something in the project

C.

An action to prevent something in the project

D.

Corrective action is not related to project

If a project with a SPI of 1.8, what you tell?

A.

The project is running ahead of the schedule

B.

The project is running behind of the schedule

C.

Resources assigned to the project cost 1.8 units

D.

None

Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?

A.

Precedence Diagramming Method (PDM)

B.

Gant Cnart Diagram (GCD)

C.

Dependency Diagramming Method (DDM)

D.

Arrow Diagramming Method (ADM)

You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?

A.

Functional

B.

Balanced matrix

C.

Piojectized

D.

Strong Matrix

If a project with a CPI of 1.2, what you tell?

A.

The project is consuming fewer resources than anticipated

B.

The project is using fewer resources than anticipated.

C.

The project is falling behind.

D.

The project is running ahead of schedule.

From whom do you need to gain the formal acceptance at project closure?

A.

The customer

B.

The qualify director

C.

Project management office

D.

Project manager

A Risk Register is a part of the ________.

A.

Project Scope Statement

B.

Project Management plan

C.

Project Scheduling plan

D.

Project Charter

The intent of the risk management process group is to ________.

A.

Increase the probability of positive outcomes in the project

B.

Announce project risks

C.

Not consider risks affecting the company

D.

Announce project deliverables