PMI CA0-001 - Certified Associate in Project Management (CAPM) Certification
Who is responsibility for making sure that a message in the project team is understood
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed.
What is the cost variance?
At the end of the project, what will be the value of SV?
As part of a mid-project evaluation, your project sponsor has asked you to provide a forecast of total project cost. You should calculate the forecast using which of the following methods?
Which of the following provides a comprehensive and consistent method of controlling the project and ensuring its success?
The risk register contains which of the following?
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
What is the status of a project if the Cost Performance Index is 1.25 and the Schedule Performance Index is 0.75?
What is the function of a Project Management Office (PMO)?
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
What defines the portion of work included in a contract for items being purchased or acquired?
Draw the precedence diagram for the dependencies and activity times below to answer the question. Use AON or another technique to derive the answer using F-S relationships.
What is the critical path duration for the given schedule network?
Which quality assurance tool and technique confirms the implementation of approved change requests, corrective actions, defect repairs, and preventive actions?
Which of the following is one of the key components of the basic communications model?