Which of the following qualitative techniques involves a disciplined analysis of the event sequences that could transform a potential hazard into an accident?

A.

Failure mode and effects criticality analysis

B.

HAZOP technique

C.

Failure mode and effects analysis

D.

Preliminary Risk Analysis

Which of the following types of elicitation allows each stakeholder to freely discuss their role in a particular process?

A.

Focus group

B.

Structured interview

C.

Quick Interview

D.

Unstructured interview

Which of the following tasks cannot start until other tasks are completed?

A.

Analysis task

B.

Dependent task

C.

Predecessor task

D.

Independent task

Which of the following charts is a quality control tool to show categories of defects?

A.

Pareto chart

B.

RACI chart

C.

Gantt chart

D.

RAM chart

The, an output of the define scope process, does document the process and criteria for accepting completed products.

A.

Statement of Work

B.

Contract

C.

Project scope statement

D.

Project management plan

Which of the following is the comparison of planned project results with actual project results?

A.

Variance analysis

B.

Cost-benefit analysis

C.

Statistical Sampling

D.

Trend analysis

Which of the following is a table of all stakeholders showing the mapping of which stakeholders will contribute information to other stakeholders?

A.

RACI Chart

B.

Communications Requirements Matrix

C.

Project scope statement

D.

Organizational Breakdown Structure

Which of the following processes includes tasks and roles, risk categories, schedules for risk management activities, definitions of probability and impact, and the stakeholders' tolerances?

A.

Risk management plan

B.

Risk register

C.

Risk analysis

D.

Risk response plan

Which of the following requires that all parties in the conflict must give up something?

A.

Barrier

B.

Problem solving

C.

Withdrawal

D.

Compromising