The Recovery Time Objective (RTO), competency of team members, and complexity of the processes to be recovered are factors that will play a role in determining the level of detail contained in:

A.

Operational plans

B.

Strategic plans

C.

Crisis communication plans

D.

Emergency response plans

A strategic plan:

A.

May be supported by a separate crisis communications plan

B.

Should identify viable options to coordinate efforts of the operational teams

C.

Should contain procedures for responding to emergencies, including threats to life, or the environment

D.

May contain procedures for coordinating the transportation of personnel to alternate facilities