Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

FIDIC CCM - Certified Contract Manager

Page: 2 / 5
Total 140 questions

You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?

Choose all of the correct answers (multiple possibilities).

A.

Specify Commencement Date in the Minutes of Meeting of Contract Negotiation.

B.

Specify Commencement Date in the Contract Agreement.

C.

Specify Commencement Date in the Particular Conditions.

D.

Inform the Commencement Date to the tenderers by email, and attach that email in the list of Contract Documents.

(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))

A.

Yes, but Contractor will do so on its own risk.

B.

Yes, Contractor can start design and execution of the Works to make sure it won ' t lose any time.

C.

No, because any design or execution before the Commencement Date is prohibited in Clause 8.

D.

Yes, but Contractor will do so on Employer ' s risk.

Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?

A.

A declaration of joint and several liability

B.

A bank guarantee

C.

A surety bond

D.

A parent company guarantee

A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?

A.

True

B.

False

(Which one of the following statements regarding FIDIC Golden Principles is correct?)

A.

The Particular Conditions do not have to be drafted clearly and unambiguously, as long as the Employer understands the meaning of the risk allocation.

B.

The Particular Conditions must not change the balance of risk/reward allocation provided in the General Conditions.

C.

The Particular Conditions can be changed under the condition that the balance of risk/reward allocation provided in the General Conditions provides for significantly less risk to the Contractor.

D.

The FIDIC Golden Principles only apply to handling the General Conditions of a contract and should not be taken into account when preparing the Particular Conditions.

Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?

A.

The Contract typically becomes legally effective when the Employer issues the Letter of Acceptance to the Contractor.

B.

The General Conditions allocate the risks between the parties on a fair and equitable basis.

C.

A disproportionate amount of risks is allocated to the Contractor under the General Conditions.

D.

The Contractor provides plant and designs (except as otherwise specified) and executes the other works, all in accordance with the Contract, which includes its Proposal and the Employer ' s Requirements.

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?

A.

Yes

B.

No

(Regarding the FIDIC Red Book (edition 2017): what two answers provide for requirements regarding a notice and other communication?

Choose all of the correct answers (multiple possibilities).)

A.

If a form of communication is to qualify as a Notice, it must be identified as a notice.

B.

If the recipient ' s address differs from the address stated in the Contract Data, notices and other communications may be delivered to that other correct address.

C.

If a form of communication does not qualify as a notice but as other communication, it must be identified as such and shall include reference of provision of Contract under which it is issued (if appropriate).

D.

Notices and other communications shall be delivered to the address of the Contractor ' s Representative.

Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?

A.

" The Employer obtains the best value for money " AND " Disputes should be avoided to the extent achievable. "

B.

" Only the Employer should be the one to obtain the best value for money " AND " The Contractor/Subcontractor is paid adequately and timely in accordance with the Contract to maintain its cash flow. "

C.

" The Contractor/Subcontractor is paid adequately and in a timely manner in accordance with the Contract to maintain its cash flow " AND " The terms of the Contract are comprehensive and fair to primarily the Employer " .

D.

" The Contractor should take advantage of its bargaining power every time possible " AND " Disputes are avoided to the extent achievable, minimised when they do arise, and resolved efficiently. "

(Under FIDIC Red and Yellow Books (both editions) the Engineer must have received technical education. Is this statement true or false?)

A.

True

B.

False