FIDIC CCM - Certified Contract Manager
You are the Contract Manager in a highway project using FIDIC Red Book (edition 1999). You work for the Employer – a highway management agency. During the tender period, you are informed of a specific Commencement Date required by the directors of the agency. Which two of the following approaches to inform the tenderers of this date are clearly and unambiguously drafted?
Choose all of the correct answers (multiple possibilities).
(Based on Clause 8 in both FIDIC Yellow and Silver Books (edition 1999), is the Contractor allowed to start the design of the Works before the Commencement Date? (1 correct answer applies))
Under the FIDIC Red Book (edition 1999), if the Contractor as per Sub-Clause 14.2 has to ensure the Employer receives an Advance Payment Guarantee as per the standard model, what type of instrument should this be?
A new important feature of the FIDIC Yellow and Silver Books (edition 2017) is the inclusion of the default position that the Works or relevant part of the Works designed by the Contractor shall be fit for their ordinary purposes. Is this statement true or false?
(Which one of the following statements regarding FIDIC Golden Principles is correct?)
Which one of the following statements is NOT correct in respect of FIDIC Yellow Book (both editions)?
Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?
(Regarding the FIDIC Red Book (edition 2017): what two answers provide for requirements regarding a notice and other communication?
Choose all of the correct answers (multiple possibilities).)
Which one answer holds two statements that are both correct with regards to risks and key considerations regarding the Golden Principles?
(Under FIDIC Red and Yellow Books (both editions) the Engineer must have received technical education. Is this statement true or false?)
