Spring Sale Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: xmas50

FIDIC CCM - Certified Contract Manager

Page: 1 / 5
Total 140 questions

Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

A.

Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.

B.

The Contractor cannot terminate the Contract.

C.

The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.

D.

The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.

You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?

A.

Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.

B.

The current index or price.

C.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.

D.

Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever agreed by Parties.

(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))

A.

In all these cases, the stakeholder not performing a required action within the allocated time limit loses all of his/her related rights that he/she otherwise would have in relation to this matter.

B.

If a Party fails to perform an obligation within the allocated time limit, then the failing party shall pay damages to the other Party.

C.

In these cases, there is a " deemed " outcome if the stakeholder does not take action within the pre-set period of time – all enabling to secure continuity of contractual processes.

D.

A Party ' s failure to perform an obligation within the allocated time limit would mean that the Engineer ' s or Employer’s decision becomes automatically binding.

There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.

Which two of the following statements are NOT applicable reasons?

(Choose all correct answers — multiple possibilities)

A.

Delay the execution of the Works or a Section.

B.

Decrease the Contract Price.

C.

Adversely affect the work of the Contractor ' s Personnel.

D.

Increase the performance of the Works when completed.

(Which two statements are correct for the FIDIC Red Book (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

A.

The Contract includes the General Conditions and Particular Conditions, and no other documentation.

B.

Conditions of Contract means these General Conditions as amended by Particular Conditions.

C.

Contract Data is part of General Conditions of Contract.

D.

Contract Agreement, Letter of Acceptance and Letter of Tender are part of the Contract.

Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?

A.

Yellow Book

B.

Red Book

C.

Silver Book

D.

Yellow or Silver Book

Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?

A.

The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).

B.

The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.

C.

Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.

Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?

A.

The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

All key delivery dates of Plant and Materials.

Which two statements are correct regarding the FIDIC Red Book (edition 2017)?

A.

Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.

B.

Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.

C.

There is never a difference in effect whether in the Particular Conditions when the term " Works " is used, or when the term " works " is used.

D.

In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.

(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)

A.

The Employer and the Contractor have identified an issue and disagreement, and have agreed between themselves that they want the DAAB to provide assistance and/or informally discuss and attempt to resolve that issue/disagreement.

B.

The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer.

C.

The Employer and the Contractor have made a " joint request " in writing before the DAAB gives the requested assistance.

D.

Both Parties should be present at the meeting in which the DAAB provides assistance.