FIDIC CCM - Certified Contract Manager
Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?
You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999). There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter?
(In FIDIC contracts, a number of time limits are included for the Parties and the Engineer to perform various obligations. How are failures to comply with these time limits most typically being dealt with in these forms of contracts? [2017 Edition] (1 correct answer))
There are four reasons that the Employer/Contractor shall advise in advance each other and the Engineer of any known or future events or circumstances.
Which two of the following statements are NOT applicable reasons?
(Choose all correct answers — multiple possibilities)
(Which two statements are correct for the FIDIC Red Book (edition 2017)?
Choose all of the correct answers (multiple possibilities).)
Which FIDIC Book (edition 2017) should be considered first by an Employer that is an experienced employer who knows exactly what they want from a design & engineering perspective?
Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?
Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?
Which two statements are correct regarding the FIDIC Red Book (edition 2017)?
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
