A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

A good description of quantitative data would be as follows:

A.

There is no difference between Qualitative data and Quantitative data

B.

Quantitative data can be categorized or summarized.

C.

Quantitative data can be described graphically or numerically.

D.

Quantitative data is a subset of data randomly selected from a population; the size of a sample is usually denoted by n.

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The amount of interest paid during the fifth year of depreciation would be:

A.

$126.00

B.

$1,200.00

C.

$1,260.00

D.

$12,000.00

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What information is needed to develop a Class 2 definitive estimate?

A.

Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates

B.

Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs

C.

Square footage of facilities, factored indirects and home office costs

D.

Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

In Rensis1 4 model system, the exploitative-authoritative management style is one in which:

A.

Management makes most decisions and passes them down

B.

Informal organizations generally support the goals of the formal organization

C.

Management issues orders, but employees have some freedom to comment

D.

Management has a lot of confidence in the employees

Two of the most important things to know when planning a speech or lecture are the ______________and______________ of your audience.

A.

Motivation, professionalism

B.

Background, attitude

C.

Political preference, sense of humor

D.

Culture, understanding

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Is a rise in the price level of a good or service, or market basket of goods and/or services.

A.

escalation

B.

deflation

C.

incremental costs

D.

inflation

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

A.

8.7%

B.

8.2%

C.

4.6%

D.

8.0%

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The following question requires your selection el Scenario 1.4.150 from the right side of your split screen. using the drop down menu to reference during your response/choice of responses.

Based on your analysis, should the press be purchased?

A.

CR is not a factor in this decision

B.

Not enough data to determine

C.

No

D.

Yes

Which of the following best describes the concept of total cost management:

A.

A method of quantifying construction damages where the total job costs are subtracted from the original bid or estimate to determine the total cost amount for a claim

B.

The practices and processes utilized to manage the total life cycle cost investment in a portfolio of strategic assets

C.

A job cost system for ensuring all aspects of a particular manufacturing process are accumulated completely

D.

An integrating process that maps the fields of practice of cost engineering without linking it to project management, resource management, or accounting

Which of the following is NOT an aspect of quality management?

A.

Quality assurance

B.

Quality planning

C.

Quality checking

D.

Quality control