In order to save energy, you are going to install an automated system to switch off lights. What should be taken into consideration when installing such a system?
What is the main disadvantage of using a ToR (Top of Rack) design?
The temperature in the computer room is being increased from 18°C/64°F to 27°C/81°F.
What is the impact, if any, on the amount of gas required to suppress a fire assuming the gas is a Halocarbon?
Management has requested a 15-minute battery bank assuming full load on the UPS. The UPS vendor has provided the following specifications of the UPS:
•Rated power: 30 kVA
•Rectifier input voltage: 400 V/3 phase
•Rectifier input power factor: 0.8
•Battery rated voltage: 384 V
•Number of cells: 192
•End of discharge voltage: 308 V
•Inverter output voltage: 400 V/3 phase
•Inverter output power factor: 0.8
What information is missing to perform the battery calculation?
You are working with a customer who requires a guarantee that THDi levels coming from the UPS should not exceed more than 3% THDi. Furthermore, he wants to run a power-efficient data center. The UPS has a 6-Pulse SCR/Thyristor based rectifier. The current load on the UPS is approximately 80%. The customer indicates they are not expecting any changes on the ICT infrastructure for the next 3 years.
What should you recommend?
You need to determine the strategy for the cooling audit. All the servers are based on a front-to-rear (F-R) airflow design.
Which location for the temperature/humidity measurement should you recommend for the audit?
A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).
Will the network architecture be part of this audit?
The humidity in the computer room has changed from about 50% down to 35% Relative Humidity (RH).
What influence does this have on Electrostatic Discharge (ESD)?